Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing Online Boosting station and FHTC at Ward No-10

Project Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing Online Boosting station and FHTC at Ward No-10
Project Code CLTJJM092115581P4
Type Package
Main Project Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing online boosting station and FHTC's
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-2020-2021 Phase I & II-Providing FHTC by retrofitting/extension and augmentation of ongoing water supply scheme in Balusseri Grama Panchayath-Providing Online Boosting station and FHTC at Ward No-10-Pipeline Work-1-at Tharippakkuni mala , Areekkal meethal , Thaikkandy Meethal and Alappara.
Status On-going
District Kozhikkode
Executing Office Koyilandy PH Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 5760000
TS Number 3308/23_26_2_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/11/2023
Scheduled date of Completion as per agreement 21 Mar 2024
Expected date of Completion 21/03/2024

Processing Dates

TS Date 29 Sep 2023
Estimate Approval 25 Feb 2023
Tender Closing 12 Oct 2023
Price bid opening 13 Oct 2023

Approval Dates

Workorder Date 07 Nov 2023
NA 22 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koyilandy PH Section 1 - AE
Date: 25/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection..

Koyilandy PH Section 1 - AE
Date: 19/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection..