KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-V

Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-V
Project Code PKDKIIFB1118630P4
Type Package
Main Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-V Distribution system from JTS OHSR (PART) in Marutharoad panchayath
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 90700000
TS Number Ts/2020-2021/2020/3370
Technical specification Supply laying Distribution system to Marutharoad panchayath from OHSR at JTS OHSR 1 st bill paid amt- 506.60 Lakhs
Contractor Binu Mathew (Mob: 9446462010)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/09/2020
Scheduled date of Completion as per agreement 16 Jun 2021
Expected date of Completion 31/12/2023

Processing Dates

TS Date 05 Jun 2020
Estimate Approval 05 Jun 2020
NIT Approval 05 Jun 2020
Tender Closing 13 Jul 2020
Technichal Pre-Qualification 14 Jul 2020
Price bid opening 16 Jul 2020

Approval Dates

NA 29 Sep 2020
Workorder Date 17 Sep 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 23/04/2024

Work in progress | 97% Completed

THE WORK IS FORE CLOSED.

Chittur Project Dn - AE 2
Date: 05/05/2023

Work in progress | 97% Completed

THE WORK IS FORE CLOSED.