| Project | JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II |
|---|---|
| Project Code | KLMJJM08204208P2 |
| Type | Package |
| Main Project | JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II |
| Status | On-going |
| District | Kollam |
| Executing Office | Kadakkal PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 149300000 |
| TS Number | TS/2020-2021/2020/20370 |
| Technical specification | FHTC for House holds in Kadakkal Panchayath |
| Contractor | J & B Engineering and Construction Company (Mob: 9447715266) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/02/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 07 Jul 2022 |
| Expected date of Completion | 07/07/2022 |
| TS Date | 18 Sep 2020 |
|---|---|
| Estimate Approval | 18 Sep 2020 |
| NIT Approval | 01 Dec 2020 |
| Tender Closing | 01 Dec 2020 |
| Technichal Pre-Qualification | 01 Dec 2020 |
| Price bid opening | 01 Dec 2020 |
| Workorder Date | 08 Jan 2021 |
|---|---|
| NA | 08 Jan 2021 |
| Kadakkal PH Sn - AE |
| Date: 04/04/2026 |
Work in progress | 70% Completed
same status.
| Kadakkal PH Sn - AE |
| Date: 31/03/2026 |
Work in progress | 70% Completed
same status.