JJM (2021-24)-CWSS to Peringamala Grama panchayat

Project JJM (2021-24)-CWSS to Peringamala Grama panchayat
Project Code TVMJJM022212328
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Scheme components 1, Well cum pump house ar Thampuranvechundakayam 2, Vertical turbine pump 3, Raw water pumping main from well cum pump house to WTP at Ayiravallikunnu 4, WTP at Ayiravallikunnu(5MLD capacity)and sump (3.5LL capacity) 5, Centrifugal pump at WTP 6, Clear water pumping main to OHSR at Ayiravallikunnu 7, OHSR at Ayiravallikunnu 8, OHSR at Adiyodi Colony 9, Clear water pumping main from the existing pump house to the OHSR at Adiyodi colony 10, Centrifugal pump 11, Infilteration gallery 12, Distribution to Zone I(from the sump) 13, Distribution to Zone II,III,IV and V(from OHSR at Ayiravallikunnu) 14, Distribution to Zone V(from OHSR to Adiyodi colony) 15, Clearwater sump(2.5LL) and pump house(water from Chithara plant) 16, Clearwater pumping main from sump to OHSR at Veliyakalakunnu 17, OHSR at Veliyakalakunnu(1LL) 18, Distribution to Zone VII(from OHSR at Veliyakalakunnu) 19, Distribution from sump (2.5LL) to Zone VI 20, Centrifugal pump at sump
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 1231687000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 38885
Capacity in MLD 5.00
Actual Project Completion Date Date is not specified
Coverage Total FHTC 7777 no.

Packages

No. Project Name Location View
1 JJM 2022-24 -CWSS to Peringamala Grama Panchayath-Distribution Network of Zone - II to V- Package 13 Trivandrum Project Dn
2 JJM 2022-24 -CWSS to Peringamala Grama Panchayath-Distribution Network of Zone - V(a)- Package 14 Trivandrum Project Dn
3 JJM-CWSS to Peringamala Grama Panchayath :Clear water pumping main to OHSR at Ayiravallikunnu: Package 6 Trivandrum Project Dn
4 JJM-CWSS to Peringamala Grama Panchayath- Construction of 10.60 LL OHSR at Ayiravallykunnu -Package 7 Trivandrum Project Dn
5 JJM-CWSS to Peringamala Grama Panchayath - Construction of 1.50 LL OHSR at Adiyodicolony - Package8 Trivandrum Project Dn
6 JJM-CWSS to Peringamala Grama Panchayath- Construction of 5 MLD Water Treatment Plant and allied works : Package 4 Trivandrum Project Dn
7 JJM-CWSS to Peringamala Grama Panchayath-Distribution Network of Zone - I - Package 12 Trivandrum Project Dn
8 JJM-CWSS to Peringamala Grama Panchayath in Thiruvananthapuram district- Construction of 0.3 LL Sump and Pumphouse at Mankayam, Package 11 Trivandrum Project Dn
9 JJM-CWSS to Peringamala Grama Panchayath : Supply,Erection,Testing and Commissioning of Raw Water Pump Set in Well Cum Pump House at Thampuranvachudakayam And Clear water pump set at WTP at Ayiravallykunnu . Package 2 & 5 Trivandrum Project Dn
10 JJM-CWSS to Peringamala Grama Panchayath-Supplying.Laying,testing and Commissioning of 300mm Raw Water Pumping main-Package 3 Trivandrum Project Dn
11 JJM -WSS to Peringamala Grama Panchayath in Thiruvananthapuram district - Construction of 8.0 M dia Well Cum Pump House at Thampuranvechundakayam,-Package 1 Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Feb 2024 Package 1- well cum pump house - excavation for a depth of 7 m(6% completed). Package 2 and 5- Supply,Erection,Testing and Commissioning of Raw Water Pump Set in Well Cum Pump House at Thampuranvachudakayam And Clear water pump set at WTP at Ayiravallykunnu.(Work Awarded and work not started). Package 3--Supplying.Laying,testing and Commissioning of 300mm Raw Water Pumping main(pipe laying completed(910.5 m) and valve chamber work pending.(95% completed). Package 4-Construction of 5 MLD Water Treatment Plant and allied works - Civil Structure for sump cum pumphouse, clariflocculator and aerator completed. Raw water channel work is in progress(56% Completed). Package 6-Clear water pumping main to OHSR at Ayiravallikunnu: (Work Awarded and work not started.). Package 7-Construction of 10.60 LL OHSR at Ayiravallykunnu(Work Awarded and work not started. Approach road Land issue). Package 8-Construction of 1.50 LL OHSR at Adiyodicolony( painting work in progress)(95% completed) .Package 9-Clear water pumping main from the existing pump house to the OHSR at Adiyodi colony:((Work Awarded and work not started). Package 11-Construction of 0.3 LL Sump and Pumphouse at Mankayam( work completed final bill submitted). Package 12- -Distribution Network of Zone - 1(work completed final bill submitted). Package 13-Distribution Network of Zone - II to V(pipe line in progress. Around 124 km out of 202 km completed(72%).HTC completed-2797 nos. Package 14-Distribution Network of Zone - V(a)( pipe line work in progress . 18 km Completed GI Work pending. HTC-300 Completed. Package 17-Construction of 2.5 LLGLSR and pump house at madathara(work awarded ,not started). package 19-CSupply,Erection,Testing and Commissioning of Clear Water Pump Set at WTP site ayiravalikunnu for proposed GLSR at Madathara melemukku(work awarded ,not started). Package 20 - Supply,Erection,Testing and Commissioning of Clear Water Pump Set for proposed OHSR at Veliyankalakunnu. (work awarded ,not started). Package 22 - Supplying.Laying,testing and Commissioning of 150mm DIK9 for 17.4 km Clear Water Pumping main from Sump at Ayiravallykunu WTP to proposed GLSR at Madathara . (work awarded ,not started). Thiruvananthapuram Project AE4
07 Feb 2024 package 1- well cum pump house - excavation for a depth of 7 m(6% completed). package 2 and 5- Supply,Erection,Testing and Commissioning of Raw Water Pump Set in Well Cum Pump House at Thampuranvachudakayam And Clear water pump set at WTP at Ayiravallykunnu.(Work Awarded and work not started). package 3--Supplying.Laying,testing and Commissioning of 300mm Raw Water Pumping main(pipe laying completed(910.5 m) and valve chamber work pending.(95% completed) package 4-Construction of 5 MLD Water Treatment Plant and allied works - Civil Structure for sump cum pumphouse, clariflocculator and aerator completed. Raw water channel work is in progress(56% Completed). package 6-Clear water pumping main to OHSR at Ayiravallikunnu: (Work Awarded and work not started.) package 7-Construction of 10.60 LL OHSR at Ayiravallykunnu(Work Awarded and work not started. Approach road Land issue). package 8-Construction of 1.50 LL OHSR at Adiyodicolony( painting work in progress)(95% completed) package 9-Clear water pumping main from the existing pump house to the OHSR at Adiyodi colony:((Work Awarded and work not started) package 11-Construction of 0.3 LL Sump and Pumphouse at Mankayam( work completed final bill submitted) package 12- -Distribution Network of Zone - 1(work completed final bill submitted). package 13-Distribution Network of Zone - II to V(pipe line in progress. Around 124 km out of 202 km completed(72%).HTC completed-2797 nos package 14-Distribution Network of Zone - V(a)( pipe line work in progress . 18 km Completed GI Work pending. HTC-300 Completed. package 17-Construction of 2.5 LLGLSR and pump house at madathara(work awarded ,not started) Thiruvananthapuram Project AE4
13 Oct 2022 Overall status: 1. Package 12 : (Distribution network from Zone1) 90 mm PVC 8 kg pipe laid for a length of 6500m Thiruvananthapuram Project AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/09/2022
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/12/2023

Processing Dates

AS Date 23 Feb 2022

Other details