KIIFB-RWSS to Vallikkodu Kodumon - Replacement of damaged ACpipe from Vallikodu OH tank to Vazhamuttom kurisu transmission line and Zonekunnu to Kodumon transmission line.

Project KIIFB-RWSS to Vallikkodu Kodumon - Replacement of damaged ACpipe from Vallikodu OH tank to Vazhamuttom kurisu transmission line and Zonekunnu to Kodumon transmission line.
Project Code PTAKIIFB0418890
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Replacement of damaged AC pipe
Status Dropped
District Pathanamthitta
Executing Office Pathanamthitta PH Dn
AS Amount (Rs) 61023000
AS Number APR-4/401/2018/KIIFB
TS Amount (Rs) 61000000
TS Number TS/2019-2020/2018/8367
Total Bill Submitted (Rs) 31385702
Total Bill Paid (Rs) 21701942
Population Benefitted 5000
Capacity in MLD 1.00
Actual Project Completion Date 31 Dec 2022
Coverage Vallikodu - Kodumon areas
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-RWSS to Vallikkodu Kodumon - Replacement of damaged ACpipe from Vallikodu OH tank to Vazhamuttom kurisu transmission line and Zonekunnu to Kodumon transmission line. Konni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Sep 2022 Work was terminated, revised estimate submitted for KIIFB sanction Pathanamthitta PH Sub Dn - AEE
24 Aug 2022 work terminated and estimate of balance work submitted for sanction Konni PH Sn - AE
20 Aug 2022 work terminated . and estimate of balance work submitted for sanction Konni PH Sn - AE
16 Aug 2022 work terminated . and estimate of balance work submitted for sanction Pathanamthitta PH Dn EE
12 Aug 2022 work terminated . and estimate of balance work submitted for sanction Pathanamthitta PH Dn EE

Project Review

See All Review messages
Review Date Review Message Review Attended By
17 Feb 2022 The contract terminated due to poor progress & EE PTA directed to submit estimate for balance works for re-arranging the work at the risk & cost of the contractor SE,PHC,Thiruvalla

Duration & Sanction dates

Date of start of Project 06/01/2021
Scheduled date of Completion of the Project 03 Mar 2021
Expected date of Completion 31/03/2022

Processing Dates

AS Date 09 Apr 2018
TS Date 09 Aug 2019

Other details

Project Officers View