- Home
- 09-UWSS to Thodupuzha- Extension of pipe...
09-UWSS to Thodupuzha- Extension of pipeline in various roads in various wards of Thodupuzha Muncipality in Thodupuzha Taluk Idukki District
| Project |
09-UWSS to Thodupuzha- Extension of pipeline in various roads in various wards of Thodupuzha Muncipality in Thodupuzha Taluk Idukki District |
| Project Code |
IDKGOK03162340 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
09-UWSS to Thodupuzha -Extension of pipeline in various roads in various wards of Thodupuzha Muncipality in Thodupuzha Taluk Idukki District |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Thodupuzha PH Dn |
| AS Amount (Rs) |
7440000
|
| AS Number |
|
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
4940837 |
| Total Bill Paid (Rs) |
1808482 |
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
07 Aug 2018 |
| Coverage |
Thodupuzha Muncipality |
Packages
| No. |
Project Name |
Location |
View |
| No Packages has been added for this project. |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 17 Nov 2020 |
completed |
Thodupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
27/02/2018 |
| Scheduled date of Completion of the Project |
07 Aug 2018 |
| Expected date of Completion |
07/08/2018 |
Processing Dates
| AS Date |
29 Mar 2016 |
| TS Date |
25 Nov 2017 |
Approval Dates
| Workorder Date |
08 Feb 2018 |
| NA |
27 Feb 2018 |