State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories

Project State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories
Project Code KLMGOK092314793P1
Type Package
Main Project State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn2
Agreement Number
Agreement Date
TS Amount (Rs) 1323800
TS Number 24121/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/04/2024
Scheduled date of Completion as per agreement 07 May 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 11 Nov 2024
Estimate Approval 05 Dec 2023
NIT Approval 07 Feb 2024
Tender Closing 17 Feb 2024
Price bid opening 21 Feb 2024

Approval Dates

Workorder Date 14 Mar 2024
NA 30 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sasthamcotta WS Sn 2 HW - AE
Date: 23/12/2024

Work has been completed | 100% Completed

Work completed and bill submitted..

Sasthamcotta WS Sn 2 HW - AE
Date: 20/11/2024

Work has been completed | 100% Completed

Work completed and bill submitted..