| Project | State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories |
|---|---|
| Project Code | KLMGOK092314793P1 |
| Type | Package |
| Main Project | State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories |
| Status | On-going |
| District | Kollam |
| Executing Office | Sasthamcottah WS Sn2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 1323800 |
| TS Number | 24121/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 09/04/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 07 May 2024 |
| Expected date of Completion | Date is not specified |
| TS Date | 11 Nov 2024 |
|---|---|
| Estimate Approval | 05 Dec 2023 |
| NIT Approval | 07 Feb 2024 |
| Tender Closing | 17 Feb 2024 |
| Price bid opening | 21 Feb 2024 |
| Workorder Date | 14 Mar 2024 |
|---|---|
| NA | 30 Mar 2024 |
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 23/12/2024 |
Work has been completed | 100% Completed
Work completed and bill submitted..
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 20/11/2024 |
Work has been completed | 100% Completed
Work completed and bill submitted..