| Project | State plan-Budget Proposal - UWSS to Nedumangad - Augmentation and enhancing the distribution networks Nedumangad Municipal area-Reach 2-Pipe line work. |
|---|---|
| Project Code | TVMGOK12218640P4 |
| Type | Package |
| Main Project | Budget Proposal 2021-22 -UWSS to Nedumangad-Augmentation and Improvement of water supply to Nedumangad |
| Funding Agency | GOK |
| Category | Urban Water Supply Schemes – Rehabilitation |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | State plan-Budget Proposal - UWSS to Nedumangad - Augmentation and enhancing the distribution networks Nedumangad Municipal area-Reach 2-Pipe line work. |
| Status | On-going |
| District | Thiruvananthapuram |
| Executing Office | Nedumangad WW Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 10327800 |
| TS Number | 1871/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 14/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 25 Dec 2023 |
| Expected date of Completion | 25/07/2024 |
| TS Date | 26 Apr 2023 |
|---|---|
| Estimate Approval | 26 Apr 2023 |
| NIT Approval | 26 Apr 2023 |
| Tender Closing | 23 May 2023 |
| Technichal Pre-Qualification | 24 May 2023 |
| Price bid opening | 24 May 2023 |
| Workorder Date | 14 Jun 2023 |
|---|---|
| NA | 26 Jun 2023 |
| Nedumangad AE |
| Date: 05/09/2024 |
Work has been completed | 100% Completed
completed .
| Nedumangad AE |
| Date: 04/09/2024 |
Work in progress | 60% Completed
180m laying completed.