DEPOSIT-Rwss to West-Kallada Gramapanchayat --Construction of pump house,Power allocation charges, Supply and erection of Pump set, Providing pumping main - near Thengumthara junction, South of Kadappakuzhi at ward no 12

Project DEPOSIT-Rwss to West-Kallada Gramapanchayat --Construction of pump house,Power allocation charges, Supply and erection of Pump set, Providing pumping main - near Thengumthara junction, South of Kadappakuzhi at ward no 12
Project Code KLMDEPO102416690
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Rwss to West-Kallada Gramapanchayat --Construction of pump house,Power allocation charges, Supply and erection of Pump set, Providing pumping main - near Thengumthara junction, South of Kadappakuzhi at ward no 12
Status Completed
District Kollam
Executing Office Sasthamcottah WS sub Dn
AS Amount (Rs) 597500
AS Number SC1/100/2024-25
TS Amount (Rs) 597500
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage West kallada Panchayath

Packages

No. Project Name Location View
No Packages has been added for this project.

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Apr 2025 Work completed Sasthamcotta WS Sn 2 HW - AE
13 Mar 2025 Work in Progress..looking forwarded for getting electric connection. Sasthamcotta WS Sn 2 HW - AE
10 Mar 2025 Work in Progress..looking forwarded for getting electric connection. Sasthamcotta WS Sn 2 HW - AE
18 Dec 2024 Work started. Sasthamcotta WS Sn 2 HW - AE
16 Nov 2024 Tender opened and LOA Preparation under progress Sasthamcotta WS Sub-Dn - AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/10/2024
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 30 Sep 2024

Other details