Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

REBUILD-MACE OF RWSS TO WEST KALLADA-PROVIDING DISINFECTION ARRANGEMENTS IN ULLURUPPIL PUMP HOUSE AT WEST KALLADA PANCHAYATGeneral Civil Work

Project REBUILD-MACE OF RWSS TO WEST KALLADA-PROVIDING DISINFECTION ARRANGEMENTS IN ULLURUPPIL PUMP HOUSE AT WEST KALLADA PANCHAYATGeneral Civil Work
Project Code KLMRKI032216788P1
Type Package
Main Project REBUILD-MACE OF RWSS TO WEST KALLADA-PROVIDING DISINFECTION ARRANGEMENTS IN ULLURUPPIL PUMP HOUSE AT WEST KALLADA PANCHAYATGeneral Civil Work
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description REBUILD-MACE OF RWSS TO WEST KALLADA-PROVIDING DISINFECTION ARRANGEMENTS IN ULLURUPPIL PUMP HOUSE AT WEST KALLADA PANCHAYATGeneral Civil Work
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn2
Agreement Number
Agreement Date
TS Amount (Rs) 30187
TS Number 16695/2024-2025
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 21 Oct 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sasthamcotta WS Sn 2 HW - AE
Date: 16/01/2025

Work has been completed | 100% Completed

Work completed. Bill submitted . .

Sasthamcotta WS Sn 2 HW - AE
Date: 15/01/2025

Work has been completed | 100% Completed

Work Completed. Bill under preparation..