- Home
- JJM-WSS to Ramamangalam Marady and Pampa...
JJM-WSS to Ramamangalam Marady and Pampakuda
Project |
JJM-WSS to Ramamangalam Marady and Pampakuda |
Project Code |
EKMJJM022211001 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
WSS to Ramamangalam Marady and Pampakuda |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
1184338000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
24900000 |
TS Number |
TS/2021-2022/2022/5162 |
Total Bill Submitted (Rs) |
10087447 |
Total Bill Paid (Rs) |
10087447 |
Population Benefitted |
|
Capacity in MLD |
12.25 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Ramamanglam Marady Pampakuda panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM- WSS to Ramamangalam, Marady and Pambakuda (part) Panchayaths in Ernakulam District-Providing FHTC to all houses - Part -I - Production Components- WTP At Methipara,Well cum Pump house at Methipara & OHSR at Methipara |
Project Division Perumbavoor |
|
2 |
JJM - WSS to Ramamangalam, Marady and Pambakuda Panchayaths - Laying 450mm Raw water pumping main 335m through Kumarakom - Nedumbassery road at Methipara. - General civil work |
Project Division Piravom(Kattapana) |
|
3 |
JJM - WSS to Ramamangalam, Marady and Pambakuda (part) Panchayaths in Ernakulam District - Part - II - providing functional house connections to all house holds, construction of OHSRs , Laying Distribution lines etc. - General civil work |
Project Division Piravom(Kattapana) |
|
4 |
JJM-WSS to Ramamangalam Marady and Pampakuda Phase 2 part 1-Laying distribution lines along KSTP road in ramamangalam panchayath |
Project Division Piravom(Kattapana) |
|
5 |
JJM-WSS to Ramamangalam , Marady & Pampakkuda (Part)-Package - I-Part - B - Well cum Pump house at Methipara , OHSR at Methipara WTP site, RWP & CWP ,Electrical instalations and allied works |
Project Division Perumbavoor |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
Laying 450 mm RWPM- 75%. Pipe 100% supplied,Laying of 450 mm in progress.200 m completed. KSTP -90%.pipe laying progress. Part II-Laying of distribution lines 90mm PVC progressing.Supplied 100 mm & 150 mm DI pipe.PART-I -work tenderd |
Piravom Project Dn AE 1 |
|
07 Sep 2023 |
Laying 450 mm RWPM- 25%. Laying distribution along KSTP -80%. Part II-Designing of OHSR,GLSR & Sump-cum-Pumphouse are in progress. Field survey with contractor in marady panchayath are held on 2/9/2023.Meeting with marady panchayth members at marady panchayath office are done on 5/9/2023. PVC pipes will be delivered by 2 nd week of September.PART-I -work tenderd |
Piravom Project Dn AE 1 |
|
24 Aug 2023 |
Laying 450 mm RWPM- 25%. Laying distribution along KSTP -50%. Part II- Site handed over to contractor. PVC pipes will be delivered by 1st week of September. Land obtained and site cleared for the construction of OHSR and Sump-cum-pumphouse at Kakkalampara and GLSR at Virippukandam. Designing of OHSR,GLSR & Sump-cum-Pumphouse are in progress. |
Piravom Project Dn AE 1 |
|
17 Aug 2023 |
Laying 450 mm RWPM- 25%. Laying distribution along KSTP -50% Part II- Survey and design of tank are in progress.KSTP - work restared -50% laying of 160 mm PVC is in progress |
Piravom Project Dn AE 1 |
|
11 Aug 2023 |
Laying 450 mm RWPM- 25%. Laying distribution along KSTP -50% Part II- Survey and design of tank are in progress.KSTP - work restarted -50% |
Piravom Project Dn AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
31 Mar 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
15 Mar 2022 |