Project | JJM 2021-22 - Pudukkad Grama Panchayath (Phase II) - Providing FHTCs to Rural house holds by augmentation of existing scheme |
---|---|
Project Code | TCRJJM022312457P1 |
Type | Package |
Main Project | JJM WSS to Pudukkad Grama Panchayath - Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM 2021-22 - Pudukkad Grama Panchayath (Phase II) - Providing FHTCs to Rural house holds by augmentation of existing scheme |
Status | On-going |
District | Thrissur |
Executing Office | Ollur Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 237100000 |
TS Number | TS/2022-2023/2021/13332 |
Technical specification | Pudukkad Grama Panchayath (Phase II) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 10 Oct 2023 |
Expected date of Completion | 09/10/2023 |
TS Date | 15 Jul 2022 |
---|---|
Estimate Approval | 15 Jul 2022 |
Workorder Date | 10 Oct 2022 |
---|---|
NA | 02 Nov 2022 |
Ollur AE |
Date: 24/06/2024 |
Work in progress | 41% Completed
Work in progress .
Ollur AE |
Date: 13/06/2024 |
Work in progress | 41% Completed
Work in Progress.