Project | Jal Jeevan Mission -PWD ROAD RESTORATION WORKS FOR KARUMALLOOR AND KUNNUKARA PANCHAYATHS-Part 1-Pipeline Work-1 |
---|---|
Project Code | EKMJJM09218347P5 |
Type | Package |
Main Project | JJM - WSS to Karumaloor & Kunnukara panchayaths - PHASE II - Distribution system and FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | PWD ROAD RESTORATION WORKS FOR KARUMALLOOR AND KUNNUKARA PANCHAYATHS- Part 1-Pipeline Work-1 |
Status | On-going |
District | Ernakulam |
Executing Office | Perumbavoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 23100000 |
TS Number | ORDER No.: WRD/KWA-CE(CR)/EST_TS/929/2023_26_2_1 |
Technical specification | PWD ROAD RESTORATION WORKS FOR KARUMALLOOR AND KUNNUKARA PANCHAYATHS |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/02/2023 |
---|---|
Scheduled date of Completion as per agreement | 26 Oct 2023 |
Expected date of Completion | 15/11/2023 |
TS Date | 15 Feb 2023 |
---|---|
Estimate Approval | 15 Feb 2023 |
NIT Approval | 27 Feb 2023 |
Tender Closing | 01 Mar 2023 |
Technichal Pre-Qualification | 17 Apr 2023 |
Price bid opening | 02 Mar 2023 |
Workorder Date | 27 Apr 2023 |
---|---|
NA | 11 May 2023 |
Perumbavoor Project Dn AE2 |
Date: 16/10/2023 |
Work has been completed | 100% Completed
Work completed.
Perumbavoor Project Dn AE2 |
Date: 15/10/2023 |
Work in progress | 98% Completed
PWD road restoration work ongoing.