JJM-(Phase - I) - 2020-21-Mulakkulam Panchayath -Balance work-(Providing & laying GSB) - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy

Project JJM-(Phase - I) - 2020-21-Mulakkulam Panchayath -Balance work-(Providing & laying GSB) - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM08204322P2
Type Package
Main Project JJM-(Phase - I) - 2020-21-Mulakkulam Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-(Phase - I) - 2020-21-Mulakkulam Panchayath -Balance work-(Providing & laying GSB) - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Status On-going
District Kottayam
Executing Office Peruva Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1372000
TS Number ORDER No. TS/2021-2022/2022/9253Dated: 09-03-2022
Technical specification JM-(Phase - I) - 2020-21-Mulakkulam Panchayath -Balance work-(Providing & laying GSB) - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Contractor Sarakh mathew (Mob: 9946433231)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/03/2022
Scheduled date of Completion as per agreement 29 Apr 2022
Expected date of Completion 17/05/2022

Processing Dates

TS Date 09 Mar 2022
Estimate Approval 09 Mar 2022
NIT Approval 15 Mar 2022
Tender Closing 22 Mar 2022
Technichal Pre-Qualification 19 Mar 2022
Price bid opening 25 Mar 2022

Approval Dates

Workorder Date 26 Mar 2022
NA 30 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 21/10/2023

Work has been completed | 100% Completed

work completed bill submitted .

Kaduthuruthy Dn EE
Date: 20/10/2023

Work has been completed | 100% Completed

Work completed.Bill Submitted .