Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH -

Project Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH -
Project Code CLTJJM092112432
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH -
Status On-going
District Kozhikkode
Executing Office Kozhikode PH Dn
AS Amount (Rs) 7010000000
AS Number G.O.(Rt)No.489/2021/ERD
TS Amount (Rs) 161600000
TS Number 570/2022-2023
Total Bill Submitted (Rs) 34372622
Total Bill Paid (Rs) 34372622
Population Benefitted 3000
Capacity in MLD 0.01
Actual Project Completion Date Date is not specified
Coverage FHTCs proposed-8112 nos. TS No. 570/2022-2023 dated 27-08-2022
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT - KANDAPPANCHAL SCHEME.-PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - KANDAPPANCHAL SCHEME Koduvally Sn
2 Jal Jeevan Mission (JJM)-JJM-PHASE-II - WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT-PROVIDING FHTCs IN KODANCHERY GRAMA PANCHAYATH-KOOROTTUPARA SCHEME Koduvally Sn
3 Jal Jeevan Mission (JJM)-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT-PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - THUSSARAGIRI Koduvally Sn
4 JJM-PHASE-II– WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- MANJUMALA SCHEMEJJM-PHASE-II– WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- MANJUMALA SCHEME Koduvally Sn
5 JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- THEVARMALA SCHEME Koduvally Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 Kandappanchal scheme - Tank work ongoing, Korootupara scheme - work ongoing , Manjumala scheme - Pipe line laying work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - work stopped Kodually W S section - AE
09 May 2024 Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. Kodually W S section - AE
06 May 2024 Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. Kodually W S section - AE
02 May 2024 Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. Kodually W S section - AE
29 Apr 2024 Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. Kodually W S section - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/12/2022
Scheduled date of Completion of the Project 31 Aug 2023
Expected date of Completion 31/08/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 27 Aug 2022

Other details

Project Officers View