Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH -
Project |
Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - |
Project Code |
CLTJJM092112432 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT -PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - |
Status |
On-going |
District |
Kozhikkode |
Executing Office |
Kozhikode PH Dn |
AS Amount (Rs) |
7010000000
|
AS Number |
G.O.(Rt)No.489/2021/ERD |
TS Amount (Rs) |
161600000 |
TS Number |
570/2022-2023 |
Total Bill Submitted (Rs) |
34372622 |
Total Bill Paid (Rs) |
34372622 |
Population Benefitted |
3000 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
Date is not specified |
Coverage |
FHTCs proposed-8112 nos.
TS No. 570/2022-2023 dated 27-08-2022 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT - KANDAPPANCHAL SCHEME.-PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - KANDAPPANCHAL SCHEME |
Koduvally Sn |
|
2 |
Jal Jeevan Mission (JJM)-JJM-PHASE-II - WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT-PROVIDING FHTCs IN KODANCHERY GRAMA PANCHAYATH-KOOROTTUPARA SCHEME |
Koduvally Sn |
|
3 |
Jal Jeevan Mission (JJM)-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT-PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH - THUSSARAGIRI |
Koduvally Sn |
|
4 |
JJM-PHASE-II– WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- MANJUMALA SCHEMEJJM-PHASE-II– WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- MANJUMALA SCHEME |
Koduvally Sn |
|
5 |
JJM-PHASE-II – WSS TO CHATHAMANGALAM AND ADJOINING 7 PANCHAYATHS IN KOZHIKODE DISTRICT: - PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION TO KODANCHERY GRAMA PANCHAYATH- THEVARMALA SCHEME |
Koduvally Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 May 2024 |
Kandappanchal scheme - Tank work ongoing, Korootupara scheme - work ongoing , Manjumala scheme - Pipe line laying work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - work stopped |
Kodually W S section - AE |
|
09 May 2024 |
Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. |
Kodually W S section - AE |
|
06 May 2024 |
Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. |
Kodually W S section - AE |
|
02 May 2024 |
Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. |
Kodually W S section - AE |
|
29 Apr 2024 |
Kandappanchal scheme - Tank work ongoing, Korootupara scheme -Tank work ongoing , Manjumala scheme - HTC work ongoing, Thevarmala scheme - Pipe line laying work ongoing and Tank work ongoing, Thusharagiri scheme - Pipe line laying ongoing. |
Kodually W S section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/12/2022 |
Scheduled date of Completion of the Project |
31 Aug 2023 |
Expected date of Completion |
31/08/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
27 Aug 2022 |