WSS to Ambalappara Panchayath in Ottappalam Taluk.-Phase II

Project WSS to Ambalappara Panchayath in Ottappalam Taluk.-Phase II
Project Code PKDKIIFB0117643P2
Type Package
Main Project WSS to Ambalappara panchayath in Ottappalam Taluk
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description 1. Construction of 6.5 MLD WTP 2. Supply and laying CWPM 3. Construction of 12 LL OHSR 4. Supply and erection of Motor pumpset
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 11100000
TS Number 2019-20/2018/10859
Technical specification Construction of 6.5MLD WTP, 12LL OHSR, Erection of VT Pumpset -1No at intake Well, Laying CWPM, Road Restoration
Contractor Thomas K Paul (Mob: 9447061604)

Project Review

See All Review messages
Review Date Review Message Review Attended By
05 Nov 2021 Ask contractor to be prepared to tar the road as and when the rain subsides Ask contractor to be prepared to tar the road as and when the rain subsides

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
07 Oct 2021 Pending Pending KWA-Organisational Project Risk KIIFB inspection memo regarding no damages made to the road. No comments available. Pending
10 May 2021 Pending Pending Natural Calamities Related Bitmen supplied by contractor, but PWD sanction for road work obtained after rain started, hence road work can not start during mansoon No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/10/2019
Scheduled date of Completion as per agreement 31 Jan 2022
Expected date of Completion 31/01/2022

Processing Dates

TS Date 12 Jun 2019
Estimate Approval 12 Jun 2019
NIT Approval 21 Aug 2019
Tender Closing 24 Jul 2019
Technichal Pre-Qualification 27 Jul 2019
Price bid opening 03 Sep 2019

Approval Dates

Workorder Date 25 Sep 2019
NA 17 Oct 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Project Dn AE
Date: 23/02/2022

Work has been completed | 100% Completed

All works completed.

Palakkad Project Dn AE
Date: 22/02/2022

Work in progress | 98% Completed

Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor.