Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM PHASE II (2021-24) CWSS to Pulpally and Mullankolly - Augmentation of the scheme and providing Functional Household Tap Connections in Mullankolly GP

Project JJM PHASE II (2021-24) CWSS to Pulpally and Mullankolly - Augmentation of the scheme and providing Functional Household Tap Connections in Mullankolly GP
Project Code WYDJJM112212628P1
Type Package
Main Project JJM PHASE II (2021-24) CWSS to Pulpally and Mullankolly - Augmentation of the scheme and providing Functional Household Tap Connections in MULLANKOLLY GP
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Augmentation of the scheme and providing Functional Household Tap Connections in Mullankolly GP
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 468000000
TS Number TS/2022-2023/2021 /36559
Technical specification Augmentation of the scheme and providing FHTC's in Mullankolly GP
Contractor KT.Manoj (Mob: 7558043708)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/10/2022
Scheduled date of Completion as per agreement 14 Apr 2024
Expected date of Completion 31/07/2024

Processing Dates

TS Date 08 Jul 2022
Estimate Approval 15 Oct 2022
Tender Closing 19 Oct 2022
Price bid opening 13 Oct 2022

Approval Dates

Workorder Date 15 Oct 2022
NA 29 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 26/06/2024

Work in progress | 80% Completed

pipe line work progress and inter connection work progress padichira tank work progress .

Sulthan Bathery PH Sn - AE
Date: 20/06/2024

Work in progress | 79% Completed

Pipe line work progress padichira 10.5LL tank main slab and Haunch and inner coloum concrete work completed HTC 1265 and FHTC 1672.