Project | JJM PHASE II (2021-24) CWSS to Pulpally and Mullankolly - Augmentation of the scheme and providing Functional Household Tap Connections in Mullankolly GP |
---|---|
Project Code | WYDJJM112212628P1 |
Type | Package |
Main Project | JJM PHASE II (2021-24) CWSS to Pulpally and Mullankolly - Augmentation of the scheme and providing Functional Household Tap Connections in MULLANKOLLY GP |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Augmentation of the scheme and providing Functional Household Tap Connections in Mullankolly GP |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 468000000 |
TS Number | TS/2022-2023/2021 /36559 |
Technical specification | Augmentation of the scheme and providing FHTC's in Mullankolly GP |
Contractor | KT.Manoj (Mob: 7558043708) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 14 Apr 2024 |
Expected date of Completion | 31/07/2024 |
TS Date | 08 Jul 2022 |
---|---|
Estimate Approval | 15 Oct 2022 |
Tender Closing | 19 Oct 2022 |
Price bid opening | 13 Oct 2022 |
Workorder Date | 15 Oct 2022 |
---|---|
NA | 29 Oct 2022 |
Sulthan Bathery PH Dn EE |
Date: 26/06/2024 |
Work in progress | 80% Completed
pipe line work progress and inter connection work progress padichira tank work progress .
Sulthan Bathery PH Sn - AE |
Date: 20/06/2024 |
Work in progress | 79% Completed
Pipe line work progress padichira 10.5LL tank main slab and Haunch and inner coloum concrete work completed HTC 1265 and FHTC 1672.