AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITY - AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITYCONSTRUCTION OF 5LL OHSR, SUPPLY AND ERECTION OF MOTOR PUMP SETS, PUMPING MAIN, DISTRIBUTION MAIN, PIPELINE EXTENSIONS AND PROVIDING FHTCs
Project |
AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITY - AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITYCONSTRUCTION OF 5LL OHSR, SUPPLY AND ERECTION OF MOTOR PUMP SETS, PUMPING MAIN, DISTRIBUTION MAIN, PIPELINE EXTENSIONS AND PROVIDING FHTCs |
Project Code |
PKDAMRUT112213842 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2.0- 2022-23- CHITTUR -
THATTHAMANGALAM MUNICIPALITY -
AMRUT 2.0- 2022-23- CHITTUR -
THATTHAMANGALAM MUNICIPALITY CONSTRUCTION OF 5LL OHSR, SUPPLY
AND ERECTION OF MOTOR PUMP SETS,
PUMPING MAIN, DISTRIBUTION MAIN,
PIPELINE EXTENSIONS AND
PROVIDING FHTCs |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Section |
AS Amount (Rs) |
78120000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
78012000 |
TS Number |
14915/2022-2023 |
Total Bill Submitted (Rs) |
19503402 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
42774 |
Capacity in MLD |
7.70 |
Actual Project Completion Date |
28 Jul 2024 |
Coverage |
Chittur - Thathamangalam Municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITY - AMRUT 2.0- 2022-23- CHITTUR - THATTHAMANGALAM MUNICIPALITYCONSTRUCTION OF 5LL OHSR, SUPPLY AND ERECTION OF MOTOR PUMP SETS, PUMPING MAIN, DISTRIBUTION MAIN, PIPELINE EXTENSIONS AND PROVIDING FHTCs |
Chittur Section |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 May 2024 |
Providing FHTCs and Linking Distribution Pipeline works in progress in various wards. |
Chittur Sn AE1 |
|
17 May 2024 |
Providing FHTCs and Linking Distribution Pipeline works in progress in various wards. |
Chittur Sn AE1 |
|
13 May 2024 |
Providing FHTCs and Linking Distribution Pipeline works in progress in various wards. |
Chittur Sn AE1 |
|
07 May 2024 |
Providing FHTCs and Linking Distribution Pipeline works in progress in various wards. |
Chittur Sn AE1 |
|
03 May 2024 |
Providing FHTC's work aslo in progress in various wards. |
Chittur Sn AE1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/08/2023 |
Scheduled date of Completion of the Project |
28 Jul 2024 |
Expected date of Completion |
28/07/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
27 Feb 2023 |