DEPOSIT-Deposit work Karunagappally Municipality-CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension of distribution pipe line with 75 mm PVC CL3 pipe (6Kg/cm2) from Theater jn to Chittakkattuthara jn in Division - 1 of Karunagappaliy Municipality.-General Civil Work

Project DEPOSIT-Deposit work Karunagappally Municipality-CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension of distribution pipe line with 75 mm PVC CL3 pipe (6Kg/cm2) from Theater jn to Chittakkattuthara jn in Division - 1 of Karunagappaliy Municipality.-General Civil Work
Project Code KLMDEPO030416480P1
Type Package
Main Project DEPOSIT-Deposit work Karunagappally Municipality-CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension of distribution pipe line with 75 mm PVC CL3 pipe (6Kg/cm2) from Theater jn to Chittakkattuthara jn in Division - 1 of Karunagappaliy Municipality.-General Civil Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work Karunagappally Municipality-CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension of distribution pipe line with 75 mm PVC CL3 pipe (6Kg/cm2) from Theater jn to Chittakkattuthara jn in Division - 1 of Karunagappaliy Municipality.-General Civil Work
Status On-going
District Kollam
Executing Office Oachira PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 322000
TS Number WRD/KWA-CEP/EST_TS/101/2022_5_14_13
Technical specification DEPOSIT-Deposit work Karunagappally Municipality-CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension of distribution pipe line with 75 mm PVC CL3 pipe (6Kg/cm2) from Theater jn to Chittakkattuthara jn in Division - 1 of Karunagappaliy Municipality.-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/10/2024
Scheduled date of Completion as per agreement 09 Jan 2025
Expected date of Completion Date is not specified

Processing Dates

TS Date 03 Sep 2024
Estimate Approval 15 Dec 2024
NIT Approval 06 Sep 2024
Tender Closing 18 Sep 2024
Technichal Pre-Qualification 20 Sep 2024
Price bid opening 20 Sep 2024

Approval Dates

Workorder Date 25 Sep 2024
NA 04 Oct 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Oachira AE
Date: 13/03/2025

Work has been completed | 100% Completed

Work completed on 26-02-2025..

Oachira AE
Date: 10/03/2025

Work in progress | 80% Completed

Pipe laying completed. PWD D/N obtained. Interconnection to be done..