Project | KIIFB-WSS to Paingottoor Panchayath in Ernakulam District-Package 1 |
---|---|
Project Code | EKMKIIFB0219651P1 |
Type | Package |
Main Project | WRD025-31-KIIFB - WSS to Paingottor Panchayath |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB-WSS to Paingottoor Panchayath -AS Amount 28.82 Cr KIIFB-WSS to Paingottoor Panchayath in Ernakulam District-Package I components(covers Zone III & IV) 1)Construction of 6m dia intake well cum pump house at Panamkara 2)RWPM of 300mm DI K9 pipe 2650m from pump house to WTP 3)Supply and erection of raw water pump set 50HP -2 Nos 4)Supply and erection of 10HP CF clear water pump set -2nos for zone I (kulapuram) 5) Supply and erection of 15HP CF clear water pump set -2nos for zone II (Methrankoop) 6)Supply and erection of 7.5HP CF clear water pump set -28m head (zone III) for pumping to OH tank at WTP site Pothakulam -2 Nos 7)Supply and erection of 10HP CF clear water pump set -2nos for zone IV (Mavinthotty) 8)Construction of 4 mld WTP with clear water sump & pump house at Pothakulam 9)Construction of 3.50 lakhs litre OHSR at Pothakulam 10)Construction of 1.20 lakhs litre OHSR at Mavinthootty 11)Laying CWPM of 150mm DI K9 pipe from WTP to OHSR at WTP site Pothakulam(Zone III)-100m 12) Laying CWPM of 100mm DI K9 pipe from WTP to OHSR at Mavinthotty(Zone IV)-545m 9)Providing distribution system in zone III (Pothakulam)& zone IV(Mavinthotty) of Paingottoor Panchayath 10)PWD &LSGD Road Restoration 11)Power connection and other allied Electrical works 12)Flow Meter 13)Contingency |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 198984000 |
TS Number | TS/3333 |
Technical specification | 1)Construction of 6m dia intake well cum pump house at Panamkara 2)RWPM of 300mm DI K9 pipe 2650m from pump house to WTP 3)Supply and erection of raw water pump set 50HP -2 Nos 4)Supply and erection of 10HP CF clear water pump set -2nos for zone I (kulapuram) 5) Supply and erection of 15HP CF clear water pump set -2nos for zone II (Methrankoop) 6)Supply and erection of 7.5HP CF clear water pump set -28m head (zone III) for pumping to OH tank at WTP site Pothakulam -2 Nos 7)Supply and erection of 10HP CF clear water pump set -2nos for zone IV (Mavinthotty) 8)Construction of 4 mld WTP with clear water sump & pump house at Pothakulam 9)Construction of 3.50 lakhs litre OHSR at Pothakulam 10)Construction of 1.20 lakhs litre OHSR at Mavinthootty 11)Laying CWPM of 150mm DI K9 pipe from WTP to OHSR at WTP site Pothakulam(Zone III)-100m 12) Laying CWPM of 100mm DI K9 pipe from WTP to OHSR at Mavinthotty(Zone IV)-545m 9)Providing distribution system in zone III (Pothakulam)& zone IV(Mavinthotty) of Paingottoor Panchayath 10)PWD &LSGD Road Restoration 11)Power connection and other allied Electrical works 12)Flow Meter 13)Contingency |
Review Date | Review Message | Review Attended By |
---|---|---|
06 Aug 2021 | Price bids opened | SE |
29 Jul 2021 | Two offers received on 22-07-2021 in the Tender for P1, technical evaluation and QCBS score valuation completed in Circle office and submitted to CECR for PQ |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2023 |
Expected date of Completion | 31/12/2023 |
TS Date | 30 Dec 2022 |
---|---|
Estimate Approval | 30 Dec 2022 |
NIT Approval | 02 Jan 2023 |
Tender Closing | 10 Feb 2023 |
Technichal Pre-Qualification | 10 Feb 2023 |
Price bid opening | 10 Feb 2023 |
Piravam Project Sub Dn AE 2 |
Date: 27/04/2024 |
Work has started | 0% Completed
Submitted for PQ .
Piravam Project Sub Dn AE 2 |
Date: 20/04/2024 |
Work has started | 0% Completed
Submitted for PQ.