Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package V |
---|---|
Project Code | PTAKIIFB0117560P12 |
Type | Package |
Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Dedicated feeder to Thiruvalla & Kallisserry plants. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 33500000 |
TS Number | Nil |
Technical specification | Providing dedicated feeder line to Kattode, Thiruvalla & Kallisserry |
Contractor | KSEB (Mob: 9446009499) |
Review Date | Review Message | Review Attended By |
---|---|---|
23 Jan 2023 | Additional amount of Rs 10,44,105 approved by KIIFB. Funds to be released for depositing to KSEB. | EE , AEE |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
03 Jan 2022 | Pending | 01 Feb 2022 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Non approval of revised package by KIIFB. Clarification requested on status ' PARKED ' | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/08/2021 |
---|---|
Scheduled date of Completion as per agreement | 31 Aug 2022 |
Expected date of Completion | 30/03/2023 |
TS Date | 31 Aug 2020 |
---|---|
Estimate Approval | 30 Nov 2021 |
NIT Approval | 10 Nov 2021 |
Tender Closing | 11 Nov 2021 |
Technichal Pre-Qualification | 11 Nov 2021 |
Price bid opening | 11 Nov 2021 |
Workorder Date | 11 Nov 2021 |
---|---|
NA | 11 Nov 2021 |
Adoor Project Dn EE |
Date: 23/03/2023 |
Work has been completed | 100% Completed
KSEB Kalliisery submitted completion letter..
Adoor Project Dn AE3 |
Date: 22/03/2023 |
Work in progress | 70% Completed
Additional amount of Rs 10,44,105 approved by KIIFB. Funds to be released for depositing to KSEB.