KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package V

Project KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package V
Project Code PTAKIIFB0117560P12
Type Package
Main Project KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and  Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Dedicated feeder to Thiruvalla & Kallisserry plants.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 33500000
TS Number Nil
Technical specification Providing dedicated feeder line to Kattode, Thiruvalla & Kallisserry
Contractor KSEB (Mob: 9446009499)

Project Review

See All Review messages
Review Date Review Message Review Attended By
23 Jan 2023 Additional amount of Rs 10,44,105 approved by KIIFB. Funds to be released for depositing to KSEB. EE , AEE

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
03 Jan 2022 Pending 01 Feb 2022 Approval/Permissions Related (from other departments excluding road cut permission and land related) Non approval of revised package by KIIFB. Clarification requested on status ' PARKED ' No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/08/2021
Scheduled date of Completion as per agreement 31 Aug 2022
Expected date of Completion 30/03/2023

Processing Dates

TS Date 31 Aug 2020
Estimate Approval 30 Nov 2021
NIT Approval 10 Nov 2021
Tender Closing 11 Nov 2021
Technichal Pre-Qualification 11 Nov 2021
Price bid opening 11 Nov 2021

Approval Dates

Workorder Date 11 Nov 2021
NA 11 Nov 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Adoor Project Dn EE
Date: 23/03/2023

Work has been completed | 100% Completed

KSEB Kalliisery submitted completion letter..

Adoor Project Dn AE3
Date: 22/03/2023

Work in progress | 70% Completed

Additional amount of Rs 10,44,105 approved by KIIFB. Funds to be released for depositing to KSEB.