Project | JJM - Providing FHTC to Rural house holds in Kizhakambalam Panchayath Phase II-Part-III |
---|---|
Project Code | EKMJJM08203030P2 |
Type | Package |
Main Project | JJM - Providing FHTC to Rural house holds in Kizhakkambalam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2020-2021-Kizhakambalam Panchayath in Ernakulam District Phase ll-part llI -Extension of pipe line in ward no 8,12,13&14 and providing (Functional House Hold Tap Connections FHTC) |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva JJM Section |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 10000000 |
TS Number | ORDER No. TS/2021-2022/2022/11598 Dated: 28-03-2022 |
Technical specification | TS/2021-2022/2022/11598 Dated: 28-03-2022 Reg .No. 23997/2021-2022 |
Contractor | T.A Meethiyan (Mob: 9447574532) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2022 |
Expected date of Completion | 31/12/2022 |
TS Date | 28 Mar 2022 |
---|---|
Estimate Approval | 28 Mar 2022 |
NIT Approval | 28 Mar 2022 |
Tender Closing | 05 Apr 2022 |
Price bid opening | 07 Apr 2022 |
Workorder Date | 13 Apr 2022 |
---|
Pattimattom - Kunnathunadu AE |
Date: 14/06/2024 |
Work in progress | 78% Completed
Work preclosed on 14.05.2024.
Aluva PH Dn EE |
Date: 13/06/2024 |
Work in progress | 78% Completed
Work preclosed on 14.05.2024 .