NABARD- RIDF XXV - CWSS to Kunnathoor, Poruvazhy, Sooranad North Panchayaths in Kunnathoor Taluk and Thazhava, Thodiyoor, Kulasekharapuram Panchayaths in Karunagappally Taluk - Construction of 44 MLD WTP at Ambuvila in Kunnathoor.

Project NABARD- RIDF XXV - CWSS to Kunnathoor, Poruvazhy, Sooranad North Panchayaths in Kunnathoor Taluk and Thazhava, Thodiyoor, Kulasekharapuram Panchayaths in Karunagappally Taluk - Construction of 44 MLD WTP at Ambuvila in Kunnathoor.
Project Code KLMNABARD08218023P1
Type Package
Main Project NABARD RIDF-XXVII, WSS to Kunnathoor, Poruvazhy and Sooranad North Panchayats of Kunnathur Taluk and Thazhava, Thodiyur and Kulasekharapuram Panchayats of Karunagapally Taluk in Kollam District
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description NABARD- RIDF XXV - CWSS to Kunnathoor, Poruvazhy, Sooranad North Panchayaths in Kunnathoor Taluk and Thazhava, Thodiyoor, Kulasekharapuram Panchayaths in Karunagappally Taluk - Construction of 44 MLD WTP at Ambuvila in Kunnathoor.
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 613900000
TS Number TS/2022-2023/2022/21258 TS/2022-2023/2022/21304
Technical specification 44 MLD WTP using plate settler technology

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
20 Oct 2021 Pending Pending Land Related Risk Land required for the construction of 44 MLD WTP at Ambuvila not handed over by Panchayath. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/03/2022
Scheduled date of Completion as per agreement 29 May 2025
Expected date of Completion 29/05/2025

Processing Dates

TS Date 17 Jun 2022
Estimate Approval 31 May 2022
NIT Approval 16 Jun 2022
Tender Closing 23 Feb 2022
Technichal Pre-Qualification 28 Feb 2022
Price bid opening 02 Mar 2022

Approval Dates

NA 20 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 27/06/2024

Work in progress | 1% Completed

Ground levelling completed.

Kollam Project HD
Date: 26/06/2024

Work in progress | 1% Completed

Ground levelling completed.