Project | KIIFB - CWSS to Chithara Phase I - Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood |
---|---|
Project Code | KLMKIIFB09186111P1 |
Type | Package |
Main Project | KIIFB - CWSS to Chithara Phase I - Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Chithara Phase I KIIFB |
Status | On-going |
District | Kollam |
Executing Office | Madathara Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 0 |
TS Number | Ts/2021-22 |
Technical specification | Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood |
Review Date | Review Message | Review Attended By |
---|---|---|
17 Dec 2021 | ENTER TENDER DATE ETC INSTEAD OF TENDERING PROCESS | AE,AEE,EE |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/06/2021 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2021 |
Expected date of Completion | 30/06/2022 |
TS Date | 06 Nov 2021 |
---|---|
Estimate Approval | 01 Jun 2021 |
NIT Approval | 30 Jun 2021 |
Tender Closing | 30 Jun 2021 |
Technichal Pre-Qualification | 30 Jun 2021 |
Price bid opening | 30 Jun 2021 |
Workorder Date | 30 Jun 2021 |
---|---|
NA | 30 Jun 2021 |
Madathara PH Sn - AE |
Date: 24/01/2023 |
Work has started | 1% Completed
Tendered three times, No offer received. Re tendered .
Madathara PH Sn - AE |
Date: 12/09/2022 |
Work has started | 0% Completed
Work re tendered. No participants. Estimate revising proceeded.