KIIFB - CWSS to Chithara Phase I - Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood

Project KIIFB - CWSS to Chithara Phase I - Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood
Project Code KLMKIIFB09186111P1
Type Package
Main Project KIIFB - CWSS to Chithara Phase I - Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Chithara Phase I KIIFB
Status On-going
District Kollam
Executing Office Madathara Sn
Agreement Number
Agreement Date
TS Amount (Rs) 0
TS Number Ts/2021-22
Technical specification Replacement of AC pipe from Madathara Treatment Plant to Pezhummoodu and Kanjirathumood

Project Review

See All Review messages
Review Date Review Message Review Attended By
17 Dec 2021 ENTER TENDER DATE ETC INSTEAD OF TENDERING PROCESS AE,AEE,EE

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/06/2021
Scheduled date of Completion as per agreement 31 Dec 2021
Expected date of Completion 30/06/2022

Processing Dates

TS Date 06 Nov 2021
Estimate Approval 01 Jun 2021
NIT Approval 30 Jun 2021
Tender Closing 30 Jun 2021
Technichal Pre-Qualification 30 Jun 2021
Price bid opening 30 Jun 2021

Approval Dates

Workorder Date 30 Jun 2021
NA 30 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Madathara PH Sn - AE
Date: 24/01/2023

Work has started | 1% Completed

Tendered three times, No offer received. Re tendered .

Madathara PH Sn - AE
Date: 12/09/2022

Work has started | 0% Completed

Work re tendered. No participants. Estimate revising proceeded.