Deposit work - PMAGY - Scheduled Caste Development Department - Renovation of Existing Structures and Laying New Gravity Line and Distribution lines at Devikulam New Colony (Ward 2 - Panchayath Scheme)

Project Deposit work - PMAGY - Scheduled Caste Development Department - Renovation of Existing Structures and Laying New Gravity Line and Distribution lines at Devikulam New Colony (Ward 2 - Panchayath Scheme)
Project Code IDKDEPO112316854P1
Type Package
Main Project Deposit work - PMAGY - Scheduled Caste Development Department - Renovation of Existing Structures and Laying New Gravity Line and Distribution lines at Devikulam New Colony (Ward 2 - Panchayath Scheme)
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - PMAGY - Scheduled Caste Development Department - Renovation of Existing Structures and Laying New Gravity Line and Distribution lines at Devikulam New Colony (Ward 2 - Panchayath Scheme)
Status On-going
District Idukki
Executing Office Devikulam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 3540000
TS Number 27358/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/07/2025

Processing Dates

TS Date 13 Feb 2024

Approval Dates

NA 24 Jun 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Devikulam AE
Date: 30/07/2025

Work has been completed | 100% Completed

All works related to the projects are completed.

Devikulam AE
Date: 26/07/2025

Work in progress | 95% Completed

No work done.