State plan-2019-20-Rural Water supply Schemes. Water supply scheme to Cheekode and adjoining villages. Package II-Laying balance distribution lines to Vazhayur and Vazhakkad panchayaths

Project State plan-2019-20-Rural Water supply Schemes. Water supply scheme to Cheekode and adjoining villages. Package II-Laying balance distribution lines to Vazhayur and Vazhakkad panchayaths
Project Code MLPGOK06202831P4
Type Package
Main Project State plan-2020-21-water supply scheme to Cheekode and adjoining villages
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Water supply scheme to Cheekode and adjoining villages. Package II-Laying balance distribution lines to Vazhayur and Vazhakkad panchayaths
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 95000000
TS Number 5033/20-21
Technical specification laying balance distribution to vazhayur and vazhakkad panchayath and providng 1000 nos fhtc

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/11/2020
Scheduled date of Completion as per agreement 31 Dec 2021
Expected date of Completion 31/12/2022

Processing Dates

TS Date 05 Aug 2020
Estimate Approval 05 Aug 2020
NIT Approval 12 Aug 2020
Tender Closing 31 Aug 2020
Technichal Pre-Qualification 02 Sep 2020
Price bid opening 16 Sep 2020

Approval Dates

Workorder Date 23 Oct 2020
NA 05 Nov 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE6
Date: 14/06/2023

Work in progress | 78% Completed

Final bill under preparation, inter connection work on going .

Malappuram Project Dn AE6
Date: 13/06/2023

Work in progress | 78% Completed

Final bill under preparation, inter connection work on going .