| Project | Jal Jeevan Mission- Kasaragod District- Enmakaje Grama Panchayath- ARWSS to Enmakaje and adjoining Villages- Phase II - Laying distribution System and providing FHTC-Package |
|---|---|
| Project Code | KGDJJM08202940P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Kasaragod District- Enmakaje Grama Panchayath- ARWSS to Enmakaje and adjoining Villages- Phase II - Laying distribution System and providing FHTC |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Providing FHTC |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Bovikkanam WSP Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 78000000 |
| TS Number | TS/2020-2021/2020/19113 |
| Technical specification | Laying distribution System and providing FHTC |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 14/10/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 12 Apr 2021 |
| Expected date of Completion | 31/05/2022 |
| TS Date | 27 Aug 2020 |
|---|---|
| Estimate Approval | 27 Aug 2020 |
| Tender Closing | 25 Sep 2020 |
| Price bid opening | 08 Oct 2020 |
| Workorder Date | 13 Oct 2020 |
|---|---|
| NA | 21 Oct 2020 |
| Bovikkanam WSP Sn AE |
| Date: 22/06/2022 |
Work has been completed | 100% Completed
Completed.
| Bovikkanam WSP Sn AE |
| Date: 14/06/2022 |
Work has been completed | 100% Completed
Completed.