Project | Package 2 - JJM-WSS to Edayur ,Irimbiliyam Panchayaths and Valancheri Municipality -Constructing Collection Well and Collection Channel to existing Well at Kaithakkadavu |
---|---|
Project Code | MLPJJM022212050P2 |
Type | Package |
Main Project | JJM- Phase 2 IRIMBILIYAM GP- Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | work include 1- Construction of a 3 M Dia collection well I the river, 2-Connection the collection well to the main well using 800 mm DI pipes, 3-Desilting and plugging the bottom of the Well. |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 8460000 |
TS Number | TS/2022-2023/2022/1494 |
Technical specification | work include 1- Construction of a 3 M Dia collection well I the river, 2-Connection the collection well to the main well using 800 mm DI pipes, 3-Desilting and plugging the bottom of the Well. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 May 2023 |
Expected date of Completion | 31/05/2023 |
TS Date | 28 Apr 2022 |
---|---|
Estimate Approval | 25 Aug 2022 |
NIT Approval | 02 May 2022 |
Tender Closing | 05 May 2022 |
Technichal Pre-Qualification | 12 May 2022 |
Price bid opening | 26 May 2022 |
Workorder Date | 16 Jul 2022 |
---|---|
NA | 14 Jul 2022 |
Malappuram Project Dn AE3 |
Date: 25/06/2024 |
Work in progress | 57% Completed
Cover slab work completed. .
Malappuram Project Dn AE3 |
Date: 24/06/2024 |
Work in progress | 57% Completed
Cover slab work completed. .