- Home
- 19- Replacement -CARWSS to Idukki-Kanjik...
19- Replacement -CARWSS to Idukki-Kanjikuzhi-Replacing of 65/50mm GI damaged pipeline Bhoomiyamkulam- Mulakuvalli road
| Project |
19- Replacement -CARWSS to Idukki-Kanjikuzhi-Replacing of 65/50mm GI damaged pipeline Bhoomiyamkulam- Mulakuvalli road |
| Project Code |
IDKGOK02174156 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
19- Replacement -CARWSS to Idukki-Kanjikuzhi-Replacing of 65/50mm GI damaged pipeline Bhoomiyamkulam- Mulakuvalli road |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Thodupuzha PH Dn |
| AS Amount (Rs) |
2000000
|
| AS Number |
|
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
1625577 |
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
03 Dec 2018 |
| Coverage |
The pipeline is laid for a length of 3000m from bhoomiyamkulam to mulakuvally and upto mulakuvally temple. The line covers more than 50 households in either sides of the road |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Package 1 - 19- Replacement -CARWSS to Idukki-Kanjikuzhi-Replacing of 65/50mm GI damaged pipeline Bhoomiyamkulam- Mulakuvalli road |
P.H.Division Thodupuzha |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 12 Nov 2020 |
Completed |
Thodupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
13/12/2017 |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
03/12/2018 |
Processing Dates
| AS Date |
17 Feb 2016 |
| TS Date |
10 Mar 2017 |
Approval Dates
| Workorder Date |
21 Jul 2017 |
| NA |
13 Dec 2017 |