| Project | AMRUT 2.0 - Retrofitting last mile connectivity supplying & laying 90/75/63 mm pvc pipeline at various places underwater supply section 3 Kollam pipeline work |
|---|---|
| Project Code | KTMAMRUT 2122315311P1 |
| Type | Package |
| Main Project | AMRUT 2.0 - Retrofitting last mile connectivity supplying & laying 90/75/63 mm pvc pipeline at various places underwater supply section 3 Kollam pipeline work |
| Funding Agency | AMRUT 2 |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | |
| Description | AMRUT 2.0 - Retrofitting last mile connectivity supplying & laying 90/75/63 mm pvc pipeline at various places underwater supply section 3 Kollam pipeline work |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 3 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 5614000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/1157/2022_26_3_2 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/12/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jun 2024 |
| Expected date of Completion | 06/06/2024 |
| TS Date | 07 Jul 2023 |
|---|---|
| Estimate Approval | 07 Jul 2023 |
| Tender Closing | 25 Jul 2023 |
| Price bid opening | 27 Jul 2023 |
| Workorder Date | 05 Dec 2023 |
|---|---|
| NA | 07 Dec 2023 |
| Kollam WS Sn 3 - AE |
| Date: 30/09/2026 |
Work in progress | 99% Completed
Pipe laying work in progress, 4030.1 m pipe laid..
| Kollam WS Sn 3 - AE |
| Date: 28/09/2026 |
Work in progress | 99% Completed
Pipe laying work in progress, 4030.1 m pipe laid..