Package 1 - JJM-Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath -Phase-2

Project Package 1 - JJM-Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath -Phase-2
Project Code MLPJJM022212050P1
Type Package
Main Project JJM- Phase 2 IRIMBILIYAM GP- Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description This work includes Laying 8.5 KM additional pipe line to cover 100% saturation and Relacing existing 250 mm AC pipe line with new 250 mm DI K-9 Pipe lines
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 60000000
TS Number TS/2022-2023/2021/27452
Technical specification 1655 FHTCs, 8500m Pipe line extension and 250 mm AC replacement with 250 mm DI pipe (4000 m)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/12/2022
Scheduled date of Completion as per agreement 31 May 2023
Expected date of Completion 31/05/2023

Processing Dates

TS Date 07 Jul 2022
Estimate Approval 07 Jul 2022
NIT Approval 15 Jul 2022
Tender Closing 09 Sep 2022
Technichal Pre-Qualification 15 Sep 2022
Price bid opening 10 Oct 2022

Approval Dates

Workorder Date 27 Oct 2022
NA 04 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 20/06/2024

Work in progress | 60% Completed

Pipe laying and connection work in progress .

Malappuram Project Dn AE3
Date: 19/06/2024

Work in progress | 60% Completed

Pipe laying and connection work in progress .