Project | Package 1 - JJM-Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath -Phase-2 |
---|---|
Project Code | MLPJJM022212050P1 |
Type | Package |
Main Project | JJM- Phase 2 IRIMBILIYAM GP- Providing Functional house hold tap connections and Pipe line works in Irimbiliyam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | This work includes Laying 8.5 KM additional pipe line to cover 100% saturation and Relacing existing 250 mm AC pipe line with new 250 mm DI K-9 Pipe lines |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 60000000 |
TS Number | TS/2022-2023/2021/27452 |
Technical specification | 1655 FHTCs, 8500m Pipe line extension and 250 mm AC replacement with 250 mm DI pipe (4000 m) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 May 2023 |
Expected date of Completion | 31/05/2023 |
TS Date | 07 Jul 2022 |
---|---|
Estimate Approval | 07 Jul 2022 |
NIT Approval | 15 Jul 2022 |
Tender Closing | 09 Sep 2022 |
Technichal Pre-Qualification | 15 Sep 2022 |
Price bid opening | 10 Oct 2022 |
Workorder Date | 27 Oct 2022 |
---|---|
NA | 04 Nov 2022 |
Malappuram Project Dn AE3 |
Date: 20/06/2024 |
Work in progress | 60% Completed
Pipe laying and connection work in progress .
Malappuram Project Dn AE3 |
Date: 19/06/2024 |
Work in progress | 60% Completed
Pipe laying and connection work in progress .