Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-Jal Jeevan Mission -2022-23 - WSS to Panjal Panchayath in Thrissur District .- Providing Distribution Network and FHTC to Panjal Panchayath

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission -2022-23 - WSS to Panjal Panchayath in Thrissur District .- Providing Distribution Network and FHTC to Panjal Panchayath
Project Code TCRJJM052213980
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission -2022-23 - WSS to Panjal Panchayath in Thrissur District .- Providing Distribution Network and FHTC to Panjal Panchayath
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 772617000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 479300000
TS Number WRD/KWA-CE(CR)/EST_TS/514/2022_5_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 25024
Capacity in MLD 4.52
Actual Project Completion Date 01 Feb 2024
Coverage Providing Distribution Network and FHTC to Panjal Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission -2022-23 - WSS to Panjal Panchayath in Thrissur District .-Construction of 11.5LL GLSR at Valarthukadu-General Civil Work Nattika Project Dn
2 Jal Jeevan Mission (JJM)-Jal Jeevan Mission -2022-23 - WSS to Panjal Panchayath in Thrissur District .- Providing Distribution Network and FHTC to Panjal Panchayath Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Jun 2024 160mm (6kg)PVC = 3171m 110mm(6kg)PVC = 7682m 90mm(6kg)PVC = 19965m 75mm(6kg)PVC = 10642m 63mm(6kg)PVC = 8307m 50mm(6kg)PVC = 1380m 160mm (8kg)PVC = 1449m 110mm (8kg)PVC =4083m 90mm (8kg)PVC = 10007m 75mm(8kg) PVC = 5582m 63mm(8kg)PVC = 4747m 50mm(8kg) PVC = 346m 80mm G I pipe = 101.75m 65mm G I pipe = 34.50m 50mm G I pipe = 28m Cumulative : 77557.05 m / 160967m, HTC - 1906/2856 Nos Road Restoration=8474.5/138279 m, Geotracking - 77512/77557.05m Nattika Project Dn AE 5
20 Jun 2024 160mm (6kg)PVC = 3171m 110mm(6kg)PVC = 7682m 90mm(6kg)PVC = 19965m 75mm(6kg)PVC = 10642m 63mm(6kg)PVC = 8307m 50mm(6kg)PVC = 1380m 160mm (8kg)PVC = 1449m 110mm (8kg)PVC =4083m 90mm (8kg)PVC = 10007m 75mm(8kg) PVC = 5582m 63mm(8kg)PVC = 4747m 50mm(8kg) PVC = 346m 80mm G I pipe = 101.75m 65mm G I pipe = 34.50m 50mm G I pipe = 28m Cumulative : 77557.05 m / 160967m, HTC - 1906/2856 Nos Road Restoration=8474.5/138279 m, Geotracking - 77512/77557.05m Nattika Project Dn AE 5
19 Jun 2024 160mm (6kg)PVC = 3171m 110mm(6kg)PVC = 7682m 90mm(6kg)PVC = 19965m 75mm(6kg)PVC = 10642m 63mm(6kg)PVC = 8307m 50mm(6kg)PVC = 1380m 160mm (8kg)PVC = 1449m 110mm (8kg)PVC =4083m 90mm (8kg)PVC = 10007m 75mm(8kg) PVC = 5582m 63mm(8kg)PVC = 4747m 50mm(8kg) PVC = 346m 80mm G I pipe = 101.75m 65mm G I pipe = 34.50m 50mm G I pipe = 28m Cumulative : 77557.05 m / 160967m, HTC - 1901/2856 Nos Road Restoration=8474.5/138279 m, Geotracking - 77512/77557.05m Nattika Project Dn AE 5
18 Jun 2024 160mm (6kg)PVC = 3171m 110mm(6kg)PVC = 7682m 90mm(6kg)PVC = 19965m 75mm(6kg)PVC = 10642m 63mm(6kg)PVC = 8307m 50mm(6kg)PVC = 1380m 160mm (8kg)PVC = 1449m 110mm (8kg)PVC =4083m 90mm (8kg)PVC = 10007m 75mm(8kg) PVC = 5582m 63mm(8kg)PVC = 4747m 50mm(8kg) PVC = 346m 80mm G I pipe = 101.75m 65mm G I pipe = 34.50m 50mm G I pipe = 28m Cumulative : 77557.05 m / 160967m, HTC - 1899/2856 Nos Road Restoration=8474.5/138279 m, Geotracking - 77512/77557.05m Nattika Project Dn AE 5
17 Jun 2024 160mm (6kg)PVC = 3171m 110mm(6kg)PVC = 7682m 90mm(6kg)PVC = 19965m 75mm(6kg)PVC = 10642m 63mm(6kg)PVC = 8307m 50mm(6kg)PVC = 1380m 160mm (8kg)PVC = 1449m 110mm (8kg)PVC =4083m 90mm (8kg)PVC = 10007m 75mm(8kg) PVC = 5582m 63mm(8kg)PVC = 4747m 50mm(8kg) PVC = 346m 80mm G I pipe = 101.75m 65mm G I pipe = 34.50m 50mm G I pipe = 28m Cumulative : 77557.05 m / 160967m, HTC - 1899/2856 Nos Road Restoration=8474.5/138279 m, Geotracking - 77512/77557.05m Nattika Project Dn AE 5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/02/2023
Scheduled date of Completion of the Project 01 Feb 2024
Expected date of Completion 31/07/2024

Processing Dates

AS Date 13 May 2022
TS Date 04 Nov 2022

Other details

Project Officers View