I) Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16

Project I) Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16
Project Code KLMGOI0917464P2
Type Package
Main Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Construction of weir at Njnkadavu across Kallada river
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 380990000
TS Number KWA/CE(SR)/PHQ/3292/2016(PARTIV)
Technical specification Construction of Weir at Njankadavu across Kallada River including mechanical portion - Revised AS Amount Rupees 104.43 Cr., TS Amount - 38.09 Cr.

Project Review

See All Review messages
Review Date Review Message Review Attended By
09 Nov 2021 As per order G.O.(Rt)No.2094/2021/LSGD Dated 26/10/2021 the original estimate amount of Rs 25.85Cr was revised to Rs 33.75Cr. Later as per further orders and with respect to the DSR 2018, the amount was revised to Rs 38.09Cr.

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/06/2020
Scheduled date of Completion as per agreement 31 Aug 2022
Expected date of Completion 30/06/2023

Processing Dates

TS Date 02 Nov 2021
Estimate Approval 28 Jan 2019
NIT Approval 28 Jan 2019
Tender Closing 04 Jan 2020
Technichal Pre-Qualification 21 Jan 2020
Price bid opening 24 Jan 2020

Approval Dates

Workorder Date 10 Mar 2020
NA 04 Jun 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 16/10/2026

Work has started | 0% Completed

The project was removed from Amrut 1.0 . Revised AS as per order no. G.O(Rt)No. 2764/2025/LSGD dated 10.11.2025 for an AS amount of 60.6 Cr has been accorded for the said work under AMRUT 2.0. A letter was sent to the Irrigation Department, the implementing department, on 17/12/2025 to prepare and submit the detailed estimate with design for according TS and arrangements of work. Irrigation department not yet submitted the DPR or estimate and AMRUT and Kollam municipal Corporation authorities planned to arrange the work directlly through Irrigation Department or KIIDC ltd. The Superintending Engineer has given a letter to the Managing Director vide letter no. KWA/PHC/KLM/WEIR/D2/3715 dated 19/9/2026 for the consideration of SHPSC approval regarding the Technical Sanction, Tendering, Execution of agreement and bill payments through Irrigation Department itself. .

Kollam Project Dn EE
Date: 13/10/2026

Work has started | 0% Completed

The project was removed from Amrut 1.0 . Revised AS as per order no. G.O(Rt)No. 2764/2025/LSGD dated 10.11.2025 for an AS amount of 60.6 Cr has been accorded for the said work under AMRUT 2.0. A letter was sent to the Irrigation Department, the implementing department, on 17/12/2025 to prepare and submit the detailed estimate with design for according TS and arrangements of work. Irrigation department not yet submitted the DPR or estimate and AMRUT and Kollam municipal Corporation authorities planned to arrange the work directlly through Irrigation Department or KIIDC ltd. The Superintending Engineer has given a letter to the Managing Director vide letter no. KWA/PHC/KLM/WEIR/D2/3715 dated 19/9/2026 for the consideration of SHPSC approval regarding the Technical Sanction, Tendering, Execution of agreement and bill payments through Irrigation Department itself. .