IV) Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira SAAP YEAR 2016-17

Project IV) Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira SAAP YEAR 2016-17
Project Code KLMGOI0917464P5
Type Package
Main Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 571100000
TS Number TS/2017-2018/2018/842 dated 7.3.18
Technical specification CONSTRUCTION OF 100 MLD PLANT HAVING CLEAR WATER RESERVOIR 43.5 LAKHS, CLARIFLOCULATOR -3 NOS 40M DIA. AERATOR, FLASHMIXER, DISTRIBUTION CHAMBER,FILTER HOUSE WITH TWIN BEDS, WASH WATER TANK, ALLIED MECHANICAL AND ELECTRICAL WORKS
Contractor M/s Ramky Vasco JV (Mob: 9447057957)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
12 Nov 2021 08 Dec 2021 Pending Natural Calamities Related The backfilling works inside the Clariflocculator was resumed by dewatering. But later, due to incessant rain further filling and compaction works were unable to proceed. Backfilling works restarted Solved
15 Sep 2021 07 Nov 2021 Pending Natural Calamities Related For the granular soil filling inside the Clariflocculator, a trial area was made inside CFL 1 as per instruction of S.E. However, it was found that since the CFL areas lies at a lower terrain with respect to the adjacent areas, and the water table level at the site is very high, continuous amount of water is replenishing the area even after continuous pumping Issue resolved by continuous dewatering and filling resumed Solved

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/11/2020
Scheduled date of Completion as per agreement 20 Jun 2020
Expected date of Completion 31/07/2023

Processing Dates

TS Date 07 Mar 2018
Estimate Approval 07 Mar 2018
NIT Approval 07 Mar 2018
Tender Closing 27 Apr 2018
Technichal Pre-Qualification 27 Apr 2018
Price bid opening 27 May 2018

Approval Dates

Workorder Date 23 Aug 2018
NA 20 Dec 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 25/03/2026

Work has been completed | 100% Completed

Work completed on 25/03/2026.

Kollam Project Dn EE
Date: 27/02/2026

Work in progress | 99% Completed

All components completed expect balance compound wallwork 70% completed and drain work 99%completed. .