IV) Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira SAAP YEAR 2016-17
| Project |
IV) Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira SAAP YEAR 2016-17 |
| Project Code |
KLMGOI0917464P5 |
| Type |
Package |
| Main Project |
22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)
|
| Funding Agency |
AMRUT |
| Category |
AMRUT |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kollam Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
571100000 |
| TS Number |
TS/2017-2018/2018/842 dated 7.3.18 |
| Technical specification |
CONSTRUCTION OF 100 MLD PLANT HAVING CLEAR WATER RESERVOIR 43.5 LAKHS, CLARIFLOCULATOR -3 NOS 40M DIA. AERATOR, FLASHMIXER, DISTRIBUTION CHAMBER,FILTER HOUSE WITH TWIN BEDS, WASH WATER TANK, ALLIED MECHANICAL AND ELECTRICAL WORKS |
| Contractor |
M/s Ramky Vasco JV (Mob: 9447057957) |
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 12 Nov 2021 |
08 Dec 2021 |
Pending |
Natural Calamities Related |
The backfilling works inside the Clariflocculator was resumed by dewatering. But later, due to incessant rain further filling and compaction works were unable to proceed. |
Backfilling works restarted |
Solved |
| 15 Sep 2021 |
07 Nov 2021 |
Pending |
Natural Calamities Related |
For the granular soil filling inside the Clariflocculator, a trial area was made inside CFL 1 as per instruction of S.E. However, it was found that since the CFL areas lies at a lower terrain with respect to the adjacent areas, and the water table level at the site is very high, continuous amount of water is replenishing the area even after continuous pumping |
Issue resolved by continuous dewatering and filling resumed |
Solved |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
01/11/2020 |
| Scheduled date of Completion as per agreement |
20 Jun 2020 |
| Expected date of Completion |
31/07/2023 |
Processing Dates
| TS Date |
07 Mar 2018 |
| Estimate Approval |
07 Mar 2018 |
| NIT Approval |
07 Mar 2018 |
| Tender Closing |
27 Apr 2018 |
| Technichal Pre-Qualification |
27 Apr 2018 |
| Price bid opening |
27 May 2018 |
Approval Dates
| Workorder Date |
23 Aug 2018 |
| NA |
20 Dec 2018 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Kollam Project Dn EE |
| Date: 25/03/2026 |
Work has been completed | 100% Completed
Work completed on 25/03/2026.
| Kollam Project Dn EE |
| Date: 27/02/2026 |
Work in progress | 99% Completed
All components completed expect balance compound wallwork 70% completed and drain work 99%completed.
.