Project | JJM - WSS to Karumaloor & Kunnukara panchayaths - PHASE II - Distribution system and FHTCs |
---|---|
Project Code | EKMJJM09218347P1 |
Type | Package |
Main Project | JJM - WSS to Karumaloor & Kunnukara panchayaths - PHASE II - Distribution system and FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Distribution system and FHTCs |
Status | On-going |
District | Ernakulam |
Executing Office | Perumbavoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 613200000 |
TS Number | TS/2021-2022/11578 |
Technical specification | providing and laying DI, PVC pipes and providing HTC connections |
Contractor | Surya constructions (Mob: 9447081789) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/07/2022 |
---|---|
Scheduled date of Completion as per agreement | 11 May 2023 |
Expected date of Completion | 11/02/2024 |
TS Date | 26 Nov 2021 |
---|---|
Estimate Approval | 26 Nov 2021 |
NIT Approval | 18 Feb 2022 |
Tender Closing | 07 Mar 2022 |
Technichal Pre-Qualification | 08 Mar 2022 |
Price bid opening | 09 Mar 2022 |
Workorder Date | 12 May 2022 |
---|---|
NA | 31 May 2023 |
Perumbavoor Project Dn AE2 |
Date: 29/06/2024 |
Work in progress | 77% Completed
connection work and tagging on going. .
Perumbavoor Project Dn AE2 |
Date: 28/06/2024 |
Work in progress | 77% Completed
connection work and tagging on going. .