Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Kuthiathode Panchayath and allied works

Project Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Kuthiathode Panchayath and allied works
Project Code ALPJJM08204189P1
Type Package
Main Project Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Kuthiathode Panchayath and allied works (1840 FHTC's)
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Kuthiathode Panchayath and allied works
Status On-going
District Alappuzha
Executing Office Thuravur PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 24490000
TS Number 6001/2020-2021
Technical specification Providing Functional House hold Tap Connections (FHTC) in Kuthiathode Panchayath and allied works (1840 FHTC's).
Contractor M/s. Michael & Michael Pipes Pvt. Ltd. (Mob: 9388223030)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/10/2020
Scheduled date of Completion as per agreement 08 Apr 2021
Expected date of Completion 31/08/2022

Processing Dates

TS Date 24 Aug 2020
Estimate Approval 24 Aug 2020
NIT Approval 27 Aug 2020
Tender Closing 04 Sep 2020
Technichal Pre-Qualification 07 Sep 2020
Price bid opening 07 Sep 2020

Approval Dates

NA 09 Oct 2020
Workorder Date 14 Sep 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Cherthala PH SUb Dn
Date: 31/12/2022

Work has been completed | 100% Completed

Final bill submitted to Divison Office.

Cherthala PH SUb Dn
Date: 31/08/2022

Work has been completed | 100% Completed

FHTCs given 1298/1840.