KIIFB- Water supply project to Peravoor,Muzhakkunnu,Payam and Ayyankunnu Panchayats in Kannur District - Phase I - Package I

Project KIIFB- Water supply project to Peravoor,Muzhakkunnu,Payam and Ayyankunnu Panchayats in Kannur District - Phase I - Package I
Project Code KNRKIIFB03187118P1
Type Package
Main Project KIIFB -WATER SUPPLY PROJECT to Peravoor, Muzhakkunnu, Payam and Ayyankunnu in Kannur District - Phase - I.
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction of Intake Well cum Pump House,Access Bridge to Intake Well,Protection and Ground filling for Transformer Yard , Transformer building,Design, Construction and Commissioning of 22MLD Water Treatment Plant, 9LL Sump cum Booster, Pump House /Watchman cabin, Compound wall,Drain,Leach pit,Approach road etc at Athithattu and 600mm Raw Water Pumping main from Intake well to Booster at Athithattu and WTP and allied structures.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No1
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Construction of Intake Well cum Pump House,Access Bridge to Intake Well,Protection and Ground filling for Transformer Yard , Transformer building,Design, Construction and Commissioning of 22MLD Water Treatment Plant, 9LL Sump cum Booster, Pump House /Watchman cabin, Compound wall,Drain,Leach pit,Approach road etc at Athithattu and 600mm Raw Water Pumping main from Intake well to Booster at Athithattu and WTP and allied structures.

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
22 Mar 2018 Pending Pending Land Related Risk Land for the construction of Booster station & WTP at Athithattu land acquisition process is in progress. Land value assessment submitted to District Collector Kannur and Contingency fund remitted to Special Tashildar LA Thalassery on 30.7.2021. The social impact study report submitted. District collector Kannur. Land for the construction of Transformer yard, Access Bridge and intake well, detailed location Sketch and report submitted to Irrigation Department. Sanction to be obtained from the Irrigation Department. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/03/2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Project Sn No 1
Date: 22/04/2024

Work has started | 0% Completed

Estimate in TS stage.

Koothuparamba Project Sn No 1
Date: 18/04/2024

Work has started | 0% Completed

Estimate in TS stage.