- Home
- Jal Jeevan Mission - WSS to Thiruvallur,...
Jal Jeevan Mission - WSS to Thiruvallur,Ayanchery,Maniyur and Cheruvannur Panchayats
Project |
Jal Jeevan Mission - WSS to Thiruvallur,Ayanchery,Maniyur and Cheruvannur Panchayats |
Project Code |
CLTJJM052211010 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction of Intake Well,Raw water Pumping main,23 MLD WTP,Transmission mains,Service Reservoirs,Distribution System and Providing FHTCs |
Status |
On-going |
District |
Kozhikkode |
Executing Office |
Vadakara PH Dn |
AS Amount (Rs) |
3715721000
|
AS Number |
G.O.(Rt)No.401/2022/WRD |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
1800000 |
Total Bill Paid (Rs) |
|
Population Benefitted |
127575 |
Capacity in MLD |
23.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Maniyur - 7165, Thiruvallur - 8700, Ayanchery - 5334, Cheruvannur - 4316 |
Packages
No. |
Project Name |
Location |
View |
1 |
Construction of 15 LL OHSR at MHES College campus Supply laying distribution net work and providing FHTC in Maniyur GP |
Vadakara WSP Sn |
|
2 |
Jal Jeevan Mission - WSS to Thiruvallur,Ayanchery,Maniyur and Cheruvannur panchayats in Kozhikode District - Laying Distribution Net work and providing FHTCs in Cheruvannur panchayat |
Perambra PH Sn |
|
3 |
Supplying, Laying and Commissioning of Distribution Network and Providing FHTCs in Thiruvallur Panchayath |
Vadakara WSP Sn |
|
4 |
Supply laying distribution net work and providing FHTC in Ayanchery GP |
Vadakara WSP Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Oct 2023 |
Thiruvalloor- pipe laying - 65.546 km, HTC- 300, Ayancheri pipe laying - 64.935 km, HTC - 340, Maniyur pipe laying - 10 km, HTC- 0, Tank work not started. |
Vatakara PH Sn - AE |
|
24 Jul 2023 |
distribution net work for Ayanchery GP supply laying works awrded |
Vatakara PH Sn - AE |
|
12 Jun 2023 |
distribution net work for Ayanchery GP supply laying works awrded |
Vatakara PH Sn - AE |
|
03 Jun 2023 |
distribution net work for Ayanchery GP supply laying works awrded |
Vatakara PH Sn - AE |
|
30 May 2023 |
distribution net work for Ayanchery GP supply laying works awrded |
Vatakara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
31 Dec 2024 |
Expected date of Completion |
31/12/2024 |