JJM 2021-22 - WSS to Thenkara panchayath Providing distribution system and FHTCs 6238 Nos
Project |
JJM 2021-22 - WSS to Thenkara panchayath Providing distribution system and FHTCs 6238 Nos |
Project Code |
PKDJJM022212336 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM 2021-22 - WSS to Thenkara panchayath - Supplying, laying, testing, commissioning and mace of distribution system with providing FHTCs 6238 Nos including road restoration |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
515598000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
262400000 |
TS Number |
TS/2022-2023/2021/15928 |
Total Bill Submitted (Rs) |
373651513 |
Total Bill Paid (Rs) |
111168113 |
Population Benefitted |
41107 |
Capacity in MLD |
4.84 |
Actual Project Completion Date |
27 Jan 2024 |
Coverage |
Thenkara panchayath in Palakkad district |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM 2021-22 - WSS to Thenkara panchayath -Providing distribution system with providing FHTCs 6238 Nos |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
110.942/139.43 km completed. Remaining PVC & DI pipe laying progressing. HTC-1745/ 6238 completed &1635 nos geo-tagged. Vadakumannam -Thathengalam road demand note received . Pooraparambu - Thathengalam Fund not allotted for BG from HO. |
Palakkad Project Dn AE |
|
22 Jun 2024 |
109.840/139.43 km completed. Remaining PVC & DI pipe laying progressing. HTC-1625/ 6238 completed & 1528 nos geo-tagged. Vadakumannam -Thathengalam road demand note received . Pooraparambu - Thathengalam Fund not allotted for BG from HO. |
Palakkad Project Dn AE |
|
20 Jun 2024 |
109.840/139.43 km completed. Remaining PVC & DI pipe laying progressing. HTC-1625/ 6238 completed & 1528 nos geo-tagged. Vadakumannam -Thathengalam road permission pending from PWD ,Re applied on ROW. Pooraparambu - Thathengalam Fund not allotted for BG from HO. |
Palakkad Project Dn AE |
|
17 Jun 2024 |
109.840/139.43 km completed. Remaining PVC & DI pipe laying progressing. HTC-1569/ 6238 completed & 1509 nos geo-tagged. Vadakumannam -Thathengalam road permission pending from PWD ,Re applied on ROW. Pooraparambu - Thathengalam Fund not allotted for BG from HO. |
Palakkad Project Dn AE |
|
15 Jun 2024 |
109.840/139.43 km completed. Remaining PVC & DI pipe laying progressing. HTC-1529/ 6238 completed & 1494 nos geo-tagged. Vadakumannam -Thathengalam road permission pending from PWD ,Re applied on ROW. Pooraparambu - Thathengalam Fund not allotted for BG from HO. |
Palakkad Project Dn AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
18 Oct 2022 |
Pending |
Pending |
Tender Call Related |
Supply and laying distribution system and FHTCs 6238 No for Thenkara panchayath using DI & PE pipes |
No comments available. |
Pending |
23 Sep 2022 |
Pending |
Pending |
Road Cut Related Risk |
Manaladi to Anamooli - 450mm DI to 90mm PE pipes are to be laid |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
16/09/2022 |
Scheduled date of Completion of the Project |
15 Jul 2023 |
Expected date of Completion |
29/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
29 Apr 2022 |