JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath

Project JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath
Project Code PKDJJM122012654
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 1591873000
AS Number 777/2020/WRD
TS Amount (Rs) 338200000
TS Number TS/2021-22/2021/44402
Total Bill Submitted (Rs) 215875434
Total Bill Paid (Rs) 162284703
Population Benefitted 6229
Capacity in MLD 22.00
Actual Project Completion Date 31 Aug 2024
Coverage TRIKKADEERI
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229nos) in Thrikkadeeri panchayath Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Nov 2024 117.8535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 3002/6229 (HTC-3001 and FHTC -1) completed & 2834 geo tagged Palakkad Project Dn AE 4
11 Nov 2024 117.7535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2997/6229 (HTC-2996 and FHTC -1) completed & 2826 geo tagged Palakkad Project Dn AE 4
07 Nov 2024 117.7535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2997/6229 (HTC-2996 and FHTC -1) completed & 2826 geo tagged Palakkad Project Dn AE 4
05 Nov 2024 117.0035 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2977/6229 (HTC-2976 and FHTC -1) completed & 2788 geo tagged Palakkad Project Dn AE 4
05 Nov 2024 117.0035 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2977/6229 (HTC-2976 and FHTC -1) completed & 2788 geo tagged Palakkad Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/10/2022
Scheduled date of Completion of the Project 12 Oct 2023
Expected date of Completion 31/05/2025

Processing Dates

AS Date 24 Nov 2022
TS Date 25 Jan 2022