JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath
Project |
JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath |
Project Code |
PKDJJM122012654 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229 nos) in Thrikkadeeri panchayath |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
1591873000
|
AS Number |
777/2020/WRD |
TS Amount (Rs) |
338200000 |
TS Number |
TS/2021-22/2021/44402 |
Total Bill Submitted (Rs) |
215875434 |
Total Bill Paid (Rs) |
162284703 |
Population Benefitted |
6229 |
Capacity in MLD |
22.00 |
Actual Project Completion Date |
31 Aug 2024 |
Coverage |
TRIKKADEERI |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - 2020 -21 -Phase ll to Chalavara,Anaganadi,Thrikkadeeri panchayaths in Palakkad District- Providing FHTC's (6229nos) in Thrikkadeeri panchayath |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2024 |
117.8535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 3002/6229 (HTC-3001 and FHTC -1) completed & 2834 geo tagged |
Palakkad Project Dn AE 4 |
|
11 Nov 2024 |
117.7535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2997/6229 (HTC-2996 and FHTC -1) completed & 2826 geo tagged |
Palakkad Project Dn AE 4 |
|
07 Nov 2024 |
117.7535 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2997/6229 (HTC-2996 and FHTC -1) completed & 2826 geo tagged |
Palakkad Project Dn AE 4 |
|
05 Nov 2024 |
117.0035 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2977/6229 (HTC-2976 and FHTC -1) completed & 2788 geo tagged |
Palakkad Project Dn AE 4 |
|
05 Nov 2024 |
117.0035 /140.24 km completed . Remaining HDPE ,PVC & DI Pipe laying work , interconnection work , gap works in progressing . KRFB permission obtained . Road restoration work on going,House connection 2977/6229 (HTC-2976 and FHTC -1) completed & 2788 geo tagged |
Palakkad Project Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/10/2022 |
Scheduled date of Completion of the Project |
12 Oct 2023 |
Expected date of Completion |
31/05/2025 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
25 Jan 2022 |