AMRUT 2022-23 Sewerage - TSS Block L - Supplying and laying 600mm pumping main from Edathara pump house to STP at Muttathara (Balance work Part - II)
Project |
AMRUT 2022-23 Sewerage - TSS Block L - Supplying and laying 600mm pumping main from Edathara pump house to STP at Muttathara (Balance work Part - II) |
Project Code |
TVMAMRUT021713358 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2022-23 Sewerage - TSS Block L - Supplying and laying 600mm pumping main from Edathara pump house to STP at Muttathara (Balance work Part - II) |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
172900000
|
AS Number |
G.O (RT)NO.534/2017/LSGD |
TS Amount (Rs) |
9668920 |
TS Number |
TS/2022-2023/2022/21425 |
Total Bill Submitted (Rs) |
20000000 |
Total Bill Paid (Rs) |
20000000 |
Population Benefitted |
15000 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
KADAKAMPALLY AREA |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2022-23 Sewerage - TSS Block L - Supplying and laying 600mm pumping main from Edathara pump house to STP at Muttathara (Balance work Part - II) |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
Completed 654 m of 600mm dia DI pipe laying out of 920m of pipes. |
Thiruvananthapuram Project AE7 |
|
07 May 2024 |
Completed 654 m of 600mm dia DI pipe laying out of 920m of pipes. |
Thiruvananthapuram Project AE7 |
|
26 Apr 2024 |
Completed 654 m of 600mm dia DI pipe laying out of 920m of pipes. |
Thiruvananthapuram Project AE7 |
|
23 Apr 2024 |
Completed 654 m of 600mm dia DI pipe laying out of 920m of pipes. |
Thiruvananthapuram Project AE7 |
|
18 Apr 2024 |
Completed 654 m of 600mm dia DI pipe laying out of 920m of pipes. |
Thiruvananthapuram Project AE7 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/08/2022 |
Scheduled date of Completion of the Project |
03 Nov 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
14 Jun 2022 |