| Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III |
|---|---|
| Project Code | KNRJJM022212626P3 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Laying distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 144800000 |
| TS Number | 9796/2022-23 |
| Technical specification | 628 Nos FHTCs |
| Contractor | K.K.SURENDRAN (Mob: 9447038315) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Dec 2023 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 30 Dec 2022 |
|---|---|
| Estimate Approval | 30 Dec 2022 |
| NIT Approval | 30 Dec 2022 |
| Tender Closing | 28 Jan 2023 |
| Technichal Pre-Qualification | 30 Dec 2022 |
| Price bid opening | 30 Jan 2023 |
| Workorder Date | 15 Mar 2023 |
|---|---|
| NA | 23 Mar 2023 |
| Mattannur Project Sn 2 AE |
| Date: 22/04/2026 |
Work in progress | 78% Completed
47 km pipe laying completed out of total quantity of pipe of 48 km. House connection and HTC work is also in progress. 172 Nos FHTC completed. 358 Nos HTC completed . construction of 0.70 LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress, up to structure completed,plastering work in progress. Road restoration 17nos. irish concrete completed.2 roads (GSB+WMM) completed.
| Mattannur Project Sn 2 AE |
| Date: 08/04/2026 |
Work in progress | 76% Completed
47 km pipe laying completed out of total quantity of pipe of 48 km. House connection and HTC work is also in progress. 172 Nos FHTC completed. 358 Nos HTC completed . construction of 0.70 LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress, up to structure completed. Road restoration 17nos. irish concrete completed.2 roads (GSB+WMM) completed.