Project | JJM - WSS to Thrikkadeeri Grama Panchayath - Additional works. |
---|---|
Project Code | PKDJJM102315825P1 |
Type | Package |
Main Project | JJM - WSS to Thrikkadeeri Grama Panchayath - Additional works. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Additional laying of 5km's Pipe Line Extension to Uncovered areas and LSGD Road Restoration works Pipe line work. |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9080000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/25916/2023 |
Technical specification | HDPE pipe PE 100 8kg ,90mm outer dia - 5km |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/03/2024 |
---|---|
Scheduled date of Completion as per agreement | 14 Sep 2024 |
Expected date of Completion | 14/09/2024 |
TS Date | 24 Nov 2023 |
---|---|
Estimate Approval | 24 Nov 2023 |
NIT Approval | 24 Nov 2023 |
Tender Closing | 27 Dec 2023 |
Price bid opening | 28 Dec 2023 |
Workorder Date | 08 Feb 2024 |
---|---|
NA | 05 Mar 2024 |
Palakkad Project Dn AE 4 |
Date: 22/06/2024 |
Work in progress | 10% Completed
PE 100,8kg 90mm dia 5000m supplied by contractor. Work not started..
Palakkad Project Dn AE 4 |
Date: 21/06/2024 |
Work in progress | 10% Completed
PE 100,8kg 90mm dia 5000m supplied by contractor. Work not started..