AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality

Project AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality
Project Code KLMAMRUT 2022313852P1
Type Package
Main Project AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality
Status On-going
District Kollam
Executing Office Oachira PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 144900000
TS Number 3048/2023-2024
Technical specification Laying 500 mm DI Clear Water Pumping Main

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/03/2026
Scheduled date of Completion as per agreement 20 Sep 2026
Expected date of Completion Date is not specified

Processing Dates

TS Date 11 May 2023
Estimate Approval 11 May 2023
Tender Closing 29 Jan 2024
Technichal Pre-Qualification 30 Jan 2024

Approval Dates

NA 18 Feb 2026

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Oachira AE
Date: 26/10/2026

Work in progress | 71% Completed

500 mm DI K9 pipe 7150 m supplied, 5136.50 m laid and balance laying work ongoing.

Oachira AE
Date: 24/10/2026

Work in progress | 71% Completed

500 mm DI K9 pipe 7150 m supplied, 5136.50 m laid and balance laying work ongoing.