KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III

Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III
Project Code PKDKIIFB1118630P3
Type Package
Main Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Package III 11.50LL OHSR at Saasthanagar- Cheraad, 250mm CWPM to this OHSR, 20LL OHSR at Vaalayakkaadu, 400mm DI CWP Common Pumping main and 350mm DI branch Pumping main, 8LL OHSR at Mundur Pth Office Compound , 250mm DI PM, Pumpsets
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 211600000
TS Number TS/2019-2020/2019/18527
Technical specification 11.50LL OHSR at Saasthanagar- Cheraad, 250mm CWPM to this OHSR, 20LL OHSR at Vaalayakkaadu, 400mm DI CWP Common Pumping main and 350mm DI branch Pumping main, 8LL OHSR at Mundur Pth Office Compound , 250mm DI PM, Pumpsets
Contractor Shaji.K.Mathew (Mob: 9447730150)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 29/06/2020
Scheduled date of Completion as per agreement 28 Jun 2021
Expected date of Completion 31/12/2023

Processing Dates

TS Date 13 Dec 2019
Estimate Approval 13 Dec 2019
NIT Approval 05 Feb 2020
Tender Closing 29 Feb 2020
Technichal Pre-Qualification 03 Mar 2020
Price bid opening 19 Mar 2020

Approval Dates

NA 14 Jul 2020
Workorder Date 29 Jun 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 23/04/2024

Work in progress | 93% Completed

Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara.

Chittur Project Dn - AE 2
Date: 11/04/2024

Work in progress | 93% Completed

Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara.