Project | KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III |
---|---|
Project Code | PKDKIIFB1118630P3 |
Type | Package |
Main Project | KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Package III 11.50LL OHSR at Saasthanagar- Cheraad, 250mm CWPM to this OHSR, 20LL OHSR at Vaalayakkaadu, 400mm DI CWP Common Pumping main and 350mm DI branch Pumping main, 8LL OHSR at Mundur Pth Office Compound , 250mm DI PM, Pumpsets |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 211600000 |
TS Number | TS/2019-2020/2019/18527 |
Technical specification | 11.50LL OHSR at Saasthanagar- Cheraad, 250mm CWPM to this OHSR, 20LL OHSR at Vaalayakkaadu, 400mm DI CWP Common Pumping main and 350mm DI branch Pumping main, 8LL OHSR at Mundur Pth Office Compound , 250mm DI PM, Pumpsets |
Contractor | Shaji.K.Mathew (Mob: 9447730150) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 29/06/2020 |
---|---|
Scheduled date of Completion as per agreement | 28 Jun 2021 |
Expected date of Completion | 31/12/2023 |
TS Date | 13 Dec 2019 |
---|---|
Estimate Approval | 13 Dec 2019 |
NIT Approval | 05 Feb 2020 |
Tender Closing | 29 Feb 2020 |
Technichal Pre-Qualification | 03 Mar 2020 |
Price bid opening | 19 Mar 2020 |
NA | 14 Jul 2020 |
---|---|
Workorder Date | 29 Jun 2020 |
Chittur Project Dn - AE 2 |
Date: 23/04/2024 |
Work in progress | 93% Completed
Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara.
Chittur Project Dn - AE 2 |
Date: 11/04/2024 |
Work in progress | 93% Completed
Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara.