RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Pavaratty & Mullassery distribution network
Project |
RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Pavaratty & Mullassery distribution network |
Project Code |
TCRRKI0320714 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Supplying, Laying, Testing and Commissioning of Distribution network of 109kms with 350mm to 80mm DI/PVC/GI pipelines for Mullassery & Pavaratty Panchayaths.
1. Distributuion network for Pavaratty and Mullassery Panchayaths. (Pavaratty Panchayath - 48kms, Mullassery Panchayath - 61kms)
2. Providing House Connections - 13576nos. (Pavaratty Panchayath - 6775nos, Mullassery Panchayath - 6801nos)
3. Construction of Steel Bridge (72m Tentative) across KLDC Canal along Elavathoor bridge |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
548000000
|
AS Number |
KWA/JB/P-2/3/2019 Part I |
TS Amount (Rs) |
447000000 |
TS Number |
TS/2020-2021/2020/18577 |
Total Bill Submitted (Rs) |
142338232 |
Total Bill Paid (Rs) |
80112904 |
Population Benefitted |
52081 |
Capacity in MLD |
3.65 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Pavaratty & Mullassery Panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
RKI -WSS to Pavaratty - Mullassery Panchayath in Chavakkad Taluk - Balance work - Interconnection |
Nattika Project Dn |
|
2 |
RKI -WSS to Pavaratty - Mullassery Panchayath in Chavakkad Taluk - Balance work - street main Extension |
Nattika Project Dn |
|
3 |
RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk (phase 2) - Supplying, laying, testing and commissioning of distribution network of 109km, with 350mm to 80mm DI/PVC/GI pipelines for Mullassery and Pavaratty Panchayaths |
Nattika Project Dn |
|
4 |
RKI-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 May 2024 |
5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. |
Nattika Project Dn AE 2 |
|
18 May 2024 |
5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. |
Nattika Project Dn AE 2 |
|
17 May 2024 |
5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. |
Nattika Project Dn AE 2 |
|
16 May 2024 |
5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. |
Nattika Project Dn AE 2 |
|
15 May 2024 |
5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. |
Nattika Project Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/03/2021 |
Scheduled date of Completion of the Project |
20 Jun 2022 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
03 Mar 2020 |
TS Date |
19 Aug 2020 |