Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Pavaratty & Mullassery distribution network

Project RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Pavaratty & Mullassery distribution network
Project Code TCRRKI0320714
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk, thrissur District- phase II - Supplying, Laying, Testing and Commissioning of Distribution network of 109kms with 350mm to 80mm DI/PVC/GI pipelines for Mullassery & Pavaratty Panchayaths. 1. Distributuion network for Pavaratty and Mullassery Panchayaths. (Pavaratty Panchayath - 48kms, Mullassery Panchayath - 61kms) 2. Providing House Connections - 13576nos. (Pavaratty Panchayath - 6775nos, Mullassery Panchayath - 6801nos) 3. Construction of Steel Bridge (72m Tentative) across KLDC Canal along Elavathoor bridge
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 548000000
AS Number KWA/JB/P-2/3/2019 Part I
TS Amount (Rs) 447000000
TS Number TS/2020-2021/2020/18577
Total Bill Submitted (Rs) 142338232
Total Bill Paid (Rs) 80112904
Population Benefitted 52081
Capacity in MLD 3.65
Actual Project Completion Date Date is not specified
Coverage Pavaratty & Mullassery Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 RKI -WSS to Pavaratty - Mullassery Panchayath in Chavakkad Taluk - Balance work - Interconnection Nattika Project Dn
2 RKI -WSS to Pavaratty - Mullassery Panchayath in Chavakkad Taluk - Balance work - street main Extension Nattika Project Dn
3 RKI - WSS to Pavaratty & Mullassery Panchayaths in Chavakad Taluk (phase 2) - Supplying, laying, testing and commissioning of distribution network of 109km, with 350mm to 80mm DI/PVC/GI pipelines for Mullassery and Pavaratty Panchayaths Nattika Project Dn
4 RKI-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 May 2024 5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. Nattika Project Dn AE 2
18 May 2024 5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. Nattika Project Dn AE 2
17 May 2024 5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. Nattika Project Dn AE 2
16 May 2024 5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. Nattika Project Dn AE 2
15 May 2024 5192m DI pipe and 104000m PVC pipe supplied out of total 109kms. 95127.25 m pipe laid. FHTC work started and 4724 nos completed in Mullassery and Pavaratty panchayath. 2.443km road is under DLP. Koombully steel bridge - work completed . Street main extension work- pipe laying 14358.4m completed. Thrithala interconnection work completed. Nattika Project Dn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/03/2021
Scheduled date of Completion of the Project 20 Jun 2022
Expected date of Completion 31/12/2023

Processing Dates

AS Date 03 Mar 2020
TS Date 19 Aug 2020

Other details

Project Officers View