Jaljeevan mission -2023-24 - Thiruvananthapuram District - Kottukal Grama Panchayath - Supplying Laying , Testing & commissioning of pipe line extension and providing Functional house hold tap connections .

Project Jaljeevan mission -2023-24 - Thiruvananthapuram District - Kottukal Grama Panchayath - Supplying Laying , Testing & commissioning of pipe line extension and providing Functional house hold tap connections .
Project Code TVMJJM092110941
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jaljeevan mission -2023-24 - Thiruvananthapuram District - Kottukal Grama Panchayath - Supplying Laying , Testing & commissioning of pipe line extension and providing Functional house hold tap connections .
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 460813100
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 201380000
TS Number TS/2021-2022/2021/42304
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD 8.00
Actual Project Completion Date Date is not specified
Coverage Kottukal Panchayath

Packages

No. Project Name Location View
1 Jaljeevan mission -2023-24 - Thiruvananthapuram District - Kottukal Grama Panchayath - Supplying Laying , Testing & commissioning of pipe line extension and providing Functional house hold tap connections . Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Aug 2022 Pipe laying work 90 mm dia.PVC Pipe of length15800m laid.and Geo tagging of 25 nos . of WSC DONE Thiruvananthapuram Project AE1
04 Aug 2022 Pipe laying work 90 mm dia.PVC Pipe of length15500 m laid.and Geo tagging of 25 nos . of WSC DONE Thiruvananthapuram Project AE1
01 Aug 2022 Pipe laying work 90 mm dia.PVC Pipe of length15500 m laid. Thiruvananthapuram Project AE1
20 Jul 2022 Pipe laying work 90 mm dia.PVC Pipe of length13500 m laid. Thiruvananthapuram Project AE1
17 Jul 2022 Pipe laying work 90 mm dia.PVC Pipe of lengt10000 m laid. Thiruvananthapuram Project AE1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/06/2022
Scheduled date of Completion of the Project 10 Mar 2023
Expected date of Completion 10/03/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 16 Dec 2021

Other details

Project Officers View