PACKAGE -IV- Construction of 21 LL, 8LL, 5 LL Capacity OHSR at Vidyangar and Pulikkunnu, Supplying and Laying gravity main from OHSR at Vidyangar to Pulikkunu

Project PACKAGE -IV- Construction of 21 LL, 8LL, 5 LL Capacity OHSR at Vidyangar and Pulikkunnu, Supplying and Laying gravity main from OHSR at Vidyangar to Pulikkunu
Project Code KGDKIIFB0117579P3
Type Package
Main Project KIIFB-WSS TO KASARAGOD MUNICIPALITY AND CHEMMANAD PANCHAYATH - PHASE I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 21 LL, 8LL, 5 LL Capacity OHSR at Vidyangar and Pulikkunnu, Supplying and Laying gravity main from OHSR at Vidyangar to Pulikkunu
Status On-going
District Kasaragod
Executing Office Project Division Kannur ( KGD)
Agreement Number
Agreement Date
TS Amount (Rs) 760000000
TS Number KWA/CE/NR/45/2016-17
Technical specification OHSR 21 LL -1 No. OHSR 8 LL -1 No. OHSR 5 LL -1 No. Gravity main - 200mm DI K9 -3420m, 300mm DI K9 -210m
Contractor K.KANNAN (Mob: 9188750611)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/10/2017
Scheduled date of Completion as per agreement 10 Sep 2018
Expected date of Completion 28/02/2022

Processing Dates

TS Date 03 Mar 2017
Estimate Approval 17 Apr 2017
NIT Approval 22 Apr 2017
Tender Closing 26 May 2017
Technichal Pre-Qualification 25 May 2017
Price bid opening 26 May 2017

Approval Dates

Workorder Date 11 Sep 2017
NA 25 Sep 2017

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kanhangad Proj Dn AEE - 1
Date: 07/10/2022

Work has been completed | 100% Completed

work completed and commissioned ,FCC submitted.

Kanhangad Proj Dn AEE - 1
Date: 29/09/2022

Work has been completed | 100% Completed

work completed and commissioned ,FCC submitted.