Project | JJM- WSS to Seethathode Laying Pipeline and Providing 1100 nos. of FHTCs in Seethathode Panchayath Phase- 1 |
---|---|
Project Code | PTAJJM022212134P1 |
Type | Package |
Main Project | JJM- WSS to Seethathode Laying Pipeline and Providing FHTCs in Seethathode Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- WSS to Seethathode Laying Pipeline and Providing 1100 nos. of FHTCs in Seethathode Panchayath Phase- 1 |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 23300000 |
TS Number | WRD/KWA-CE(SR)/EST TS/4620/2022 26 1 1 |
Technical specification | Laying Pipeline and Providing 1100 nos. of FHTCs in Seethathode Panchayath Phase- 1 |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/11/2022 |
---|---|
Scheduled date of Completion as per agreement | 02 Sep 2023 |
Expected date of Completion | 02/09/2023 |
TS Date | 28 Dec 2022 |
---|
Workorder Date | 17 Feb 2023 |
---|---|
NA | 03 Mar 2023 |
Adoor Project Dn - AE 5 |
Date: 26/06/2024 |
Work in progress | 10% Completed
Balance connections will given only after the distribution network is laid under JJM Seethathode works. (( Overall progress- 90 mm PVC pipe laid - 2979.00 m. 80 mm GI pipe laid - 54 m. House connections laid- 127 nos.).
Adoor Project Dn - AE 5 |
Date: 24/06/2024 |
Work in progress | 10% Completed
Balance connections will given only after the distribution network is laid under JJM Seethathode works. (( Overall progress- 90 mm PVC pipe laid - 2979.00 m. 80 mm GI pipe laid - 54 m. House connections laid- 127 nos.).