| Project | Jjm Ummannoor- Providing FHTC in Ummannoor panchayta- Supplying and laying additional pipe line |
|---|---|
| Project Code | KLMJJM08203133P2 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Providing FHTC at Ummannoor Grama panchayath in Kollam I District |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | IIM Ummannoor- Providing FHTC in Ummannoor panchayat- supplying and laying additional pipe line |
| Status | On-going |
| District | Kollam |
| Executing Office | Valakom PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 17183000 |
| TS Number | 2990/2022-23 |
| Technical specification | Additional pipe supply and laying |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 13/06/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 10 Nov 2022 |
| Expected date of Completion | 31/12/2024 |
| TS Date | 06 May 2022 |
|---|---|
| Estimate Approval | 06 May 2022 |
| NIT Approval | 10 May 2022 |
| Tender Closing | 23 May 2022 |
| Technichal Pre-Qualification | 23 May 2022 |
| Price bid opening | 25 May 2022 |
| Workorder Date | 13 Jun 2022 |
|---|---|
| NA | 10 Aug 2022 |
| Valakom PH Sn AE |
| Date: 17/06/2025 |
Work in progress | 87% Completed
23 KM pipe laying completed.
| Valakom PH Sn AE |
| Date: 16/04/2025 |
Work in progress | 87% Completed
23 KM pipe laying completed.